You are 5 months into a 10 month project. The project is linear, which means that the planned progress and budgeted spending occurs at a constant rate. Our crack project team of highly skilled associates has worked diligently and put in extra hours to keep the project going.  Our accounting department has provided the following data at the end of month 5:

Actual cost to date = $100,000

Planned value of work scheduledto date = $120,000

The CFO is excited and has sent you an email congratulating you for being 17% under budget. However, is it really time to hold a team celebration? That would be fun but your project manager mentality kicks in. Those numbers look good but how are we 'really' doing? To understand the true project performance, we need to apply earned value techniques.

Since we have the AC and the PV the missing piece we need is Earned Value (i.e. what we have actually accomplished so far). You meet with your team and find that only 6 of the 9 tasks scheduled to be complete have actually been completedby the end of month 5. Task 7 isn't even started! This information gives you the final data you need to apply 'Earned Value'and develop an objective analysis.

Careful. Be sure to read the problem carefully and don't make assumptions that are not given in the problem.

1.  What are the PV, EV, and AC for the project at the end of month 5?

PV=

EV =

AC=

2. What are the SV, CV, SPI, and CPI for the project?

SV=

CV=

SPI=

CPI=

3.  Assess the project performance to date? Do you get to have the celebration?

5-2 Earned Value Calculation

Your project has four activities. Below is the current status of each activity.

Activity A was to have cost $160,000 when complete. Its costs so far are $95,000. It is 45% complete. 
The activity has completed 5 weeks of a planned 8-week schedule. 

Activity B is finished. It finished 2 weeks late. It cost $135,000. And it was planned to have cost $130,000. 

Activity C is at the end of week 4 of a planned 8-week effort. It is 40% complete. It was to cost $100,000 when finished. Its costs to date are $50,000.

Activity D is at the end of week 3 of a planned 6-week schedule. It has cost $110,000 so far. It was estimated to cost $200,000 when finished. It is approximately 50% complete. 

 Using this data, calculate the following.

1. What are the PV, EV, and AC for each of the activities and the complete project?

EV

PV

AC

A

 

 

 

B

 

 

 

C

 

 

 

D

 

 

 

Project

 

 

 

2.  What are the SV, CV, SPI, and CPI for each of the activities and the complete project?

 

SV

CV

SPI

CPI

A

 

 

 

 

B

 

 

 

 

C

 

 

 

 

D

 

 

 

 

Project

 

 

 

 

3.  Assess the project performance to date? Do you get to have the celebration?

You should focus on the total project but look at the individual activities that have major effects.

Marketing Management, Management Studies

  • Category:- Marketing Management
  • Reference No.:- M92487491
  • Price:- $30

Priced at Now at $30, Verified Solution

Have any Question?


Related Questions in Marketing Management

Question 1 application of conceptstime value of money2

Question: 1. Application of concepts/time value of money? 2. Which is more detrimental to a firm, pricing your product or service too high, or pricing your product or service too low? 3. Discuss the role of demographics ...

Question imagine that you are in the market for a new

Question: Imagine that you are in the market for a new career. How can the marketing research process apply to your career search? Think of a specific topic you need to learn more about that relates to your career as a o ...

Question strategic marketing planintroductionthis

Question: STRATEGIC MARKETING PLAN INTRODUCTION This assignment entails development of a comprehensive strategic marketing plan for a new product or service that is ready to "go to market". A Project Template is provided ...

Qestion ready set strive gen z is comingby janet adamy

Question: Ready, Set, Strive : Gen Z Is Coming By Janet Adamy | Sep 07, 2018 TOPICS: Consumer Behavior, External Marketing Environment, Targeting SUMMARY: About 17 million members of Generation Z are now adults and start ...

Question in your marketing plan you should1establish a

Question: In your Marketing Plan, you should: 1. Establish a Mission Statement and a Vision Statement for your new organization. 2. Briefly describe basic services it has been providing during the first six months of ope ...

Question 1review the terminal course objectives accessed by

Question: 1. Review the Terminal Course Objectives, accessed by clicking on the "Course Information" tab at the top of your screen, scrolling down to the "Course Objectives" and then selecting View class objectives. How ...

Question read the worddoc first and answer those following

Question: Read the word.doc first and answer those following question 1. Provide a list of at least five pieces of information that airlines have about their customers, and for each, explain how that information might he ...

In this unit you are asked to produce a public relations

In this unit you are asked to produce a Public Relations Campaign Proposal document and an essay that explains the theory behind your planned approach to the Proposal task. You may base your assessment on the suggested s ...

Question 1200 words on your favorite retailer and their

Question: 1200 words on your favorite retailer and their major competitor as discussed in class. This should focus on the different elements that make up the retail strategy of the companies and other factors that appeal ...

Question bulltype of paper assignmentbullsubject

Question: • Type of paper Assignment • Subject Other • Number of pages 1 • Format of citation Other • Number of cited resource s0 • Type of service Writing from scratch First, choose a piece of art from any genre (music, ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As