Work Breakdown Structure, Scope, and PERT evaluation of email upgrade

Scenario:

Your organization has just completed the Initiation Process for implementing an Email System Upgrade. It was identified in a recent meeting with management leaders from the Sales, Consulting and IT departments that the current email system is causing significant business interruptions and must be updated. You have been assigned the role of project manager to develop the project schedule and costs. As project manager, you are responsible in implementing and enforcing the project schedule and its estimates, expected costs, and the techniques and methods that will be chosen to execute and control the project. The project is being initiated with the following initial project scope in mind:
- There are five email systems currently being used across twelve departments and offices. These will be replaced and consolidated into one email system.
- New Email Standards and Protocols will be established and training provided to all departments.
- All 2000 current email users will be converted to the new system, and 500 new users that did not have email before will be added.
- Users will have both LAN and remote access to email.
- Help desk and support infrastructure will be set-up to accommodate the new system.
- Equipment will be salvaged.
- User PCs will be upgraded to accommodate the new email system.

Tasks required for solution:

Create the WBS for the project.

Define Scope of the project

- Work Breakdown Structure (WBS) representative of the scope of work
- All major tasks, organized into work packets. Prepare estimates for the activities or work packets at this time.

Assign an initial work effort estimated in days to each of the activities.

Calculate estimates in days of work effort (not duration). Give justifications and details on assumptions, 6-8 paragraphs.

Based on the WBS and estimates, apply the standard PERT estimating formula and calculate the expected estimate (Te) for each activity. Use a table similar to the one provided to complete the estimates.

Business Management, Management Studies

  • Category:- Business Management
  • Reference No.:- M9739398

Have any Question?


Related Questions in Business Management

Name a company that addressed a recent ethical problem in a

Name a company that addressed a recent ethical problem in a positive way. Also, explain how or if this positively affects us as a community?

When it is appropriate to use the trade-off process what

When it is appropriate to use the trade-off process. What conditions apply, and the technical evaluation criteria that might be used?

Need help with a essay with the following phrase for

Need help with a essay with the following phrase for analyzing : " Capitalism is at the heart of how people and organisations are managed in contemporary society" May i ask for a better explanation of the question? Also ...

How could these three tenets of the auburn creed be used to

How could these three tenets of the Auburn Creed be used to motivate others: "I believe that this is a practical word and that I can count only on what I earn. Therefore, I believe in work, hard work." "I believe in educ ...

How can these two tenets of the auburn creed by used in

How can these two tenets of the Auburn Creed by used in addressing teamwork issues: "I believe in honesty and truthfulness, without which I cannot win the respect and confidence of my fellow men." "I believe in the human ...

Discuss the advantages of having and interacting in a

Discuss the advantages of having and interacting in a diverse workplace. Consider the wide range of ideas and perspectives that a range of team members bring to a team, that are of differing ages, ethnic backgrounds and ...

Parmigiano-reggiano global recognition of geographical

Parmigiano-Reggiano: Global Recognition of Geographical Indications What historical factors have helped support the consortium's claims for the geographic specificity of Parmigiano-Reggiano and Parmesan? What are the eco ...

Communication planthis communication plan will be a roadmap

Communication Plan This communication plan will be a roadmap on how the new division will best be able to communicate with Biotech's corporate headquarters, suppliers, other divisions, and internally. This should lay out ...

Discuss strategies to obtain feedback from a customer and

Discuss strategies to obtain feedback from a customer and clients when working in sales.

Describe different networking methods and the advantages

Describe different networking methods and the advantages and disadvantages of them?

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As