1. What is the first exterior finish that should be estimated?
a. foundation treatment
b. finishes & walls
c. roofing items
d. none of the above
2. Assuming that the floor joists are set on a 16" centers, how may joists are needed for a floor that is 49 feet long?
a. 36
b. 37
c. 38
d. 41
3. The term R-Value is ued with regards to ____
a. WTERPROOFING
B. THERMAL PROTECTION
C. STRENGH OF ANCHORS
D. SOIL PERMEABILITY
4. When doing a wall system takeoff, two extra studs are allowed at____.
a. each corner in the wall
b. the intersection of two walls
c. each opening
d. all of the above
5. Calculate the full height of sand/cement parging that will extend down to 6" below grade, based on the following data (1) average elevation of grade around building - 46.5' (2) elevation of top of floor 49.5' (3) height of joists and floor deck - 0.83'
a. 2.15'
b. 2.17'
c. 2.67'
d. 3.0'