Question 1

A member of a project team that is implementing a new credit card payment process at a bank has direct responsibility to do all of the following EXCEPT:

be sensitive to conflicts between other team members and help resolve them.

ensure that the project has appropriate resources for the job to be completed.

help solve project problems that spill over into areas outside their expertise.

be called upon to share their expertise in credit card payment processes.

Question 2

Mike Multitask has three projects (A, B, and C) that are each four days long. Mike's supervisor suggests that he work first on project A, finish it, then work on project B until it is finished, and then on project C. Mike boldly declares, "My name isn't Multitask for nothing," so he decides to spend one day working on project A, one on B, one on C, then back to project A, and so on. There is no additional start up or shut down time required by splitting the projects this way. What is the difference in average completion time for all three projects when they are managed Mike's way when compared with his supervisor's suggestion?

There is no difference.

Mike's way is 3 days shorter.

Mike's way is 3 days longer.

Mike's way is 9 days longer.

Question 3

Slack time is routinely lost in a network:

at the point where multiple paths exit a common node.

at the point where multiple paths enter a common node.

at the point where the longest activity begins.

at the point where the shortest activity begins.

Question 4

Following are four sets of most optimistic, most likely, and most pessimistic times (in weeks) for an activity. Which one of the four sets will have a mean estimated time equal to the most likely time?

1, 9, 9

1, 5, 9

1, 1, 9

1, 5, 5

Question 5

You are responsible for managing a project with the following activities (times are given in days).

Activity      Expected Time    Immediate Predecessor(s)

A                 3                            ---

B                 6                            ---

C                 2                            ---

D                 5                             A

E                  2                            C

F                   7                            A

G                   4                         B, D, E

what is the critical path and expected completion time for this project?

A - F ; 12 days

A-D-G; 12 Days

B-G; 10 days

C, E, G; 10 days

Question 6

Assuming a beta distribution is being used, if the most pessimistic time for an activity increases by six weeks, what will happen to the expected time for that activity?


It will increase by one week.

It will decrease by one week.

It will increase by six weeks.

It will remain the same.

Question 7

If the sum of the variances on the critical path (and all other network paths) is equal to zero, what is the probability that the project will be completed by its earliest expected completion date?

50 percent

95 percent

100 percent

It cannot be determined.

Question 8

A project is currently scheduled to be finished on its normal earliest completion date. The project manager has the opportunity to earn a bonus if the project can be completed three weeks ahead of schedule. The increase in project direct costs related to crashing activities would be $40,000. Also, project indirect costs are $15,000 per week. What is the smallest bonus that the project manager should accept if he or she wants to avoid increasing overall project costs?

Less than or equal to $5,000

Greater than $5000 but less than or equal to $10,000

Greater than $10,000 but less than or equal to $15,000

Greater than $15,000

Question 9

You are given the following information about activity B:
Normal time = 9 weeks
Crash time = 5 weeks
Cost to crash per week = $2000
Crash cost = $41,000

What will it cost to complete activity B in 6 weeks?

Less than or equal to $34,000

Greater than $34,000 but less than or equal to $36,000

Greater than $36,000 but less than or equal to $38,000

Greater than $38,000

Question 10

You are given the following information about activity F:
Normal time = 16 weeks
Crash time = 10 weeks
Crash cost = $45,000
Cost to crash per week = $2,000

What is the normal cost for activity F?

Greater than or equat to $55,000

Less than $55,000 but greater than or equal to $47,000

Less than $47,000 but greater than or equal to $40,000

Less than $40,000

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M9700324
  • Price:- $20

Priced at Now at $20, Verified Solution

Have any Question?


Related Questions in Operation Management

Conflictdefine functional versus dysfunctional conflict in

Conflict Define functional versus dysfunctional conflict in a work group and explain how you can increase functional conflict and decrease dysfunctional conflict. Develop a response that includes examples and evidence to ...

For this assignment you will need to find 2 articles in

For this assignment, you will need to find 2 articles in business that can help describe what are IT strategic initiative being undertaken by an organization are like. Choose a different organization for each of the arti ...

Coping with problems joe is a little nervous he has just

Coping With Problems Joe is a little nervous. He has just been transferred from another plant to take over a production line. Production is down and there is a serious problem with absenteeism. To make matters worse, the ...

Over 30 years ago michael porter identified a holistic

Over 30 years ago Michael Porter identified a holistic approach to understanding how competitive forces shape strategy. He posited that the only way to truly insulate an organization from underlying economic volatility i ...

You are the contracting officer for an air-to-ground

You are the contracting officer for an air-to-ground missile development program. A contract for pre-production models of the missile was awarded by your predecessor and the contractor is behind schedule. In a program me ...

The ikea case provides an excellent opportunity to apply

The IKEA case provides an excellent opportunity to apply strategic management concepts to a large privately-held company that is expanding into India. IKEA is a Netherlands-based Swedish company with a presence in 44 cou ...

Can you answer for me the following questions about social

Can you answer for me the following questions about social loafing and the three main causes of free-riding. 1. Give a description of the phenomenon of social loafing. 2. Give a description of the phenomenon of free-ridi ...

1 analyzing the bridgestonefirestone and ford motor company

1. Analyzing the Bridgestone/Firestone and Ford motor company, is it sufficient to use the ISO/QS 9000 standards as the main basis of vendor/product selection? 2. What position to these cars company ( 1. Volkswagen, 2. F ...

Research the effect of primary and secondary seat belt laws

Research the effect of primary and secondary seat belt laws on the occurrence of motor-vehicle injuries and fatalities. Explain how epidemiologic studies influenced the development of current seat belt laws. Describe how ...

Please provide a brief paragrap of the key takaways from

Please provide a brief paragrap of the key takaways from each of the following topics: Designing Clear Visuals in business reports Designing Successful Documents and Websites Writing Winning Proposals

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As