A company is preparing a bid on a private contract for 50 projects of software applications. The operations manager of the bidding company estimates the project time required for the third and sixth projects to be 150 hours and 112.5 hours respectively. Using this information and the Learning Curve Rule, determine the appropriate learning curve?