The times need to finish each of eight jobs in a two-machine flow shops are given in the table which follows. Each job should follow same sequence, beginning with machine A and moving to Machine B.

1) Find out a sequence which will minimize span time.

2) Create a chart of resulting sequence, and determine machine B’s idle time.

3) For the sequence determine in part a, how much would machine B’s idle time be decreased by slitting last two jobs in half?

TIME (HOURS)

JOB   Machine A    Machine B
A            16                 5
B             3                 13
C             9                  6
D             8                  7
E             2                 14
F           12                  4
G          18                 14
H          20                  11

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M910173

Have any Question? 


Related Questions in Operation Management

During its first year of operations silverman company paid

During its first year of operations, Silverman Company paid $10,285 for direct materials and $9,800 for production workers' wages. Lease payments and utilities on the production facilities amounted to $8,800 while genera ...

With regard to the reluctant workers case study is the

With regard to the reluctant workers case study, is the problem about management or leadership style or lack of project management skills?

The normal time to perform a repetitive manual assembly

The normal time to perform a repetitive manual assembly task is 4.25 min. In addition, an irregular work element whose normal time is 1.75 min must be performed every 8 cycles. Two work units are produced each cycle. The ...

You are required to research and choose articles relevant

You are required to research and choose articles relevant to blending a diverse workforce and post the article or link to an article for everyone to read. The post must include a summary of salient points that will entic ...

A paint shop implements an inventory policy on its stock of

A paint shop implements an inventory policy on its stock of white paint, which costs the store $6 per can. Monthly demand for cans of white paint is normal with mean 28 and standard deviation 8. The replenishment lead ti ...

Dalmar has worked for 22 years at a 40-employee branch of a

Dalmar has worked for 22 years at a 40-employee branch of a large auto parts chain. Business has been very bad lately, and there are rumors of consolidation, reorganization, and even bankruptcy. Which protection is Dalma ...

Each question should have a 1 page typed response direct

Each question should have a 1 page (typed) response. Direct copying of the text, websites, or other sources is not acceptable. There are 6 questions on the exam. Questions 1 -5 count 16 points each. Question 6 counts 20 ...

Explain what bait and switch is and why it is an example of

Explain what bait and switch is and why it is an example of deceptive pricing. Have you ever been a victim of this practice? 250 words please

Franklin a us born individual of english ancestry works for

Franklin, a U.S. born individual of English ancestry, works for the China Lights restaurant, which is owned and operated by two U.S. citizens of Chinese ancestry. Franklin's coworkers Jin Pan and Dongping Jiang, also U.S ...

Please address the following three needs assessment factors

Please address the following three needs assessment factors in three double-spaced pages (four maximum): Explain the importance of focusing on improved performance in the needs assessment process. Describe why data colle ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Section onea in an atwood machine suppose two objects of

SECTION ONE (a) In an Atwood Machine, suppose two objects of unequal mass are hung vertically over a frictionless

Part 1you work in hr for a company that operates a factory

Part 1: You work in HR for a company that operates a factory manufacturing fiberglass. There are several hundred empl

Details on advanced accounting paperthis paper is intended

DETAILS ON ADVANCED ACCOUNTING PAPER This paper is intended for students to apply the theoretical knowledge around ac

Create a provider database and related reports and queries

Create a provider database and related reports and queries to capture contact information for potential PC component pro

Describe what you learned about the impact of economic

Describe what you learned about the impact of economic, social, and demographic trends affecting the US labor environmen