The project manager has just received a change from the customer that does not affect the project schedule and is easy to complete. What should the project manager do FIRST?

A. Make the change happen as soon as possible

B. Contact the project sponsor for permission

C. Go to the change control board

D. Evaluate the impacts on other project constraints

Business Management, Management Studies

  • Category:- Business Management
  • Reference No.:- M91770149
  • Price:- $10

Priced at Now at $10, Verified Solution

Have any Question?


Related Questions in Business Management

For this first assignment you will be writing a brief

For this first assignment, you will be writing a brief response to the Gilded Age primary sources linked below, all of which deal with the experience of workers and immigrants during this period of vast economic change. ...

A new machine averages 4 clock cycles per instruction and

A new machine averages 4 clock cycles per instruction, and runs at a system clock of 20 MHz. The Axiom-Verge algorithm set to benchmark the system will take an even 3000 instructions to complete. a) Knowing how many cloc ...

What are some of the differences between a manager and a

What are some of the differences between a Manager and a Leader, and why is his distinction so important?

1 what is the pepsico business model2 what is the reason

1. What is the PepsiCo business model? 2. What is the reason for incorporating the lean approach at PepsiCo? 3. What is the planning process for lean management operations in (PepsiCo)? 4. How to implement an information ...

Refers to factors that impact the distribution channels in

Refers to factors that impact the distribution channels in ways that are directly related to the amount of influence, as when channel members have on one another, such as lobbying efforts by channel member associations l ...

Looking at how bp initially handled the gulf oil spill when

Looking at how BP initially handled the Gulf oil spill when the Deepwater Horizon drilling platform exploded in April 2010. Specifically, note how the company dealt with the clean-up process, those directly impacted by t ...

Why is it important to engage on sustainabilityis it

Why is it important to engage on sustainability? Is it possible for stakeholder relationship to be only one-way? Discuss What is meant by a ladder of stakeholder engagement?

What are your thoughts on reasonable accommodation do you

What are your thoughts on reasonable accommodation? Do you feel as if the company you work for meets or exceeds the reasonable accommodation standard?

1a how are your strengths and weaknesses in self-management

1.(a) How are your strengths and weaknesses in self-management impacting your work performance and relationships with co-workers and consumers and List one step you can take to improve your self-awareness.? (b) How are y ...

How do you think diversity communication and organisational

How do you think diversity, communication and organisational structure could potentially constitute strong aspects of organisational culture? Why is it important for the manager to consider this relationship?

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As