Q. Nine (9) welders who perform the identical short-cycle job were observed by a time + motion engineer over four (4) cycles every. The total time recorded was 2-hundred-ten (210) minutes. The performance rating for a particular welder was established at ninety-2 % (92% ). Additionally, every welder is granted a twelve % (12%) allowance for personal needs, fatigue also routine delays.
1. Elucidate what is observed time (OT) for this job
2. Elucidate what is normal time (NT) for the selected welder
3 Elucidate what is the standard time (ST) for the selected welder hide problem