A Project has just completed the 87th item in its action plan. It was scheduled to have spent $168,000 at this point in the plan but has actually spent only $156,000. The foreman estimates that the value of the work actually finished is about $162, 000. What are the spending and schedule variances for the project? What are the SPI and CPI?

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M983467

Have any Question?


Related Questions in Operation Management

To critically analyze and discuss four different policies

To critically analyze and discuss FOUR different policies with each of the four determinants of national competitive advantage that will attract Multinational Corporations (MNCs) and protect domestic firms in your countr ...

A few years ago mark and phil thought it would be fun to

A few years ago Mark and Phil thought it would be fun to work together on a piece of research. They also hoped it would benefit their continuing development as researchers. Mark’s research background (strength) has its o ...

1 what was the nature of benefits derived by walmart from

1. What was the nature of benefits derived by Walmart from the efficient supply chain management practices and how far it has contributed to its sustainable competitive advantage? Explain. 2. Walmart invited its major su ...

You are president of a 50m metal component

You are President of a $50M metal component fabrication/assembly business. –100% Family Owned: Dad just retired (with a lot of knowledge), two kids (youngest is a sales rep) –The market is very competitive. Product is of ...

1 what policies should an hr executive review or consider

1. What policies should an HR executive review or consider when their company is pursuing a strategy of global expansion? 2. Should HR executives be more concerned about vertical or horizontal alignment when a company is ...

1 shipments of product x from a plant to a wholesaler are

1. Shipments of Product X from a plant to a wholesaler are made in lots of 600. The wholesaler's average demand for X is 100 units per week. The lead time from the plant to the wholesaler is 4 weeks. The wholesaler pays ...

1 discuss three problems that can arise during strategy

1. Discuss three problems that can arise during strategy implementation. How can an organization overcome these problems? 2. Describe how changes in technology contributed to the globalization of markets. 3. Explain how ...

1 if average demand is 20 units per day with a standard

1. If average demand is 20 units per day with a standard deviation of 4 units, and if average lead time is 8 days with a standard deviation of 2 days, what should the reorder point be to ensure a 97.72% inventory availab ...

1 the case involving new haven connecticut fighters ricci v

1) The case involving New Haven Connecticut fighters, Ricci v. DeStefano. What's an employer to do? The fire department management it thought the promotion exam had a disparate impact on minorities, and they threw out th ...

1 what are your thoughts on the concept of respondeat

1. What are your thoughts on the concept of respondeat superior? 2. What does writing persuasively mean to you? What techniques do you think an effective persuasive writer should use in his/her writing? 3. What is the pu ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As