Q. My professor desires it to be done in Excel format which shows the graph also table. Please help.
The Electrotech Corporation manufactures two industrial-sized electrical devices: generators also alternators. Both of these products need wiring also testing during the assembly process. Each generator needs 2 hours of wiring also 1 hour of testing also can be sold for a $250 profit. There are 260 hours of wiring time also 140 hours of testing time available in the next production period also Electrotech desires to maximize profit.
A. Formulate also LP model for this problem
B. Sketch the feasible region for the problem
C. Conclude the optimal solution to this problem utilizing level curves.