1. Set this Exercise project plan toTask Type Fixed Duration. Start the project on December 1. Use the default Standard Calendar with no holidays.

2. Enter the following task names and durations.  Be sure the Timescale is set to Month/Year (Middle Tier) and Weeks (Bottom Tier).  Also, summarize tasks into phases.

Plan Phase

Plan the Project                      3d

Gather Requirements                8d

Review Requirements                2d

Design Phase

Design Feasibility Study            12d

Design / Analysis                     17d

Build Prototype Phase

1st Generation Build                  12d

Competitive Engine Evaluation    17d

Customer Input                       7d

Test Phase

1st Life Test                           32d

Final Design Life Test               17d

Performance Development         10d

Field Test                              32d

Production Rollout                   0d

3. Save the file with the following filename format, "Assign4 yymmdd,"  ie. Assign4DOlson171024.

4. Link the tasks shown below. Note that some tasks have more than one predecessor.

Task

Predecessor(s)

Plan the Project

 

Gather Requirements

Plan the Project

Review Requirements

Gather Requirements

 

 

Design Feasibility Study

Review Requirements

Design/Analysis

Design Feasibility Study

 

 

1st Generation Build

Design Feasibility Study

Competitive Engine Evaluation

1st Generation Build

Customer Input

1st Generation Build

 

 

1st Life Test

Design/Analysis

Competitive Engine Evaluation

Customer Input

Final Design Life Test

1st Life Test

Performance Development

Final Design Life Test

Field Test

Final Design Life Test

 

 

Production Rollout

Performance Development

Field Test

Assign the following Resources and Work estimates to the tasks listed below.  Use $50/hour as the rate for all resources.

Be sure that the project plan has the Task Type Fixed Duration. 

Task                                        Resource Name                     Work

 

Plan the Project                     Project Leader                    8h

                                          Design Engineer                   4h

                                          Product Marketing                4h

                                          Production Supervisor           4h

                                          Quality Control Specialist       4h

 

Gather Requirements              Project Leader                       16h

                                         Design Engineer                      8h

                                         Product Marketing                   8h

                                         Production Supervisor              8h

                                         Quality Control Specialist          8h

 

Review Requirements             Project Leader                        8h

                                         Design Engineer                      4h

                                         Product Marketing                   4h

                                         Production Supervisor              4h

                                         Quality Control Specialist         4h

 

Design Feasibility Study         Design Engineer                      30h

                                         Product Marketing                  20h

 

Design/Analysis                     Design Engineer                     30h

                                         Product Engineer                    45h

                                         Tooling Engineer                     8h

 

1st Generation Build               Production Engineer               10h

                                         Production Supervisor             5h

 

Competitive Engine Eval.        Design Engineer                     15h

                                         Test Technician                    15h

                                         Quality Control Specialist        15h

                                         Product Marketing                 8h

 

Customer Input                     Product Marketing                 10h

                                         Design Engineer                     1h

 

1st Life Test                        Test Technician                     30h

                                         Production Engineer               15h

 

Final Design Life Test            Design Engineer                     15h

                                        Quality Control Specialist         15h

                                        Test Technician                     15h

 

Performance Development     Design Engineer                      16h

                                        Production Engineer                 8h

                                        Product Marketing                   4h

 

Field Test                           Test Technician                      30h

Production Rollout                                                           -None-

5. Submit the MS Project Plan to the appropriate Dropbox.  Be sure to follow the Microsoft Project Guide example and the grading rubric for settings and final submission format of the plan.

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M92509326

Have any Question?


Related Questions in Operation Management

1 what communication method would be ideal for an

1. What communication method would be ideal for an organization that has offices in many different countries? 2. Is it necessary to sacrifice speed in communication for the sake of a global presence? That is, can a compa ...

Answer each question in 75 words a piece use references if

Answer EACH question in 75 words A PIECE. Use references, if needed and cite. 1. Discuss whether or not you were aware of the differences between managers and leaders. Now that you are aware of the differences, does this ...

If you are working as a consultant for coca cola how does

If you are working as a consultant for Coca Cola, how does the dismissal of the deal by the Chinese government affect your continued investment in the country? What more could private business, like Coca Cola do to convi ...

Security with information systemsfind an information

Security with Information Systems Find an information security attack that occurred within the last three months. Explain what information was breached and when the organization notified its customers of the attack. Make ...

Typical ways in which firms organize their international

Typical ways in which firms organize their international activities are: 1) domestic structure plus export department; 2) domestic structure plus foreign subsidiary; 3) International division; 4) global functional (i.e., ...

Is cloud computing clearly better for the environment yes

Is cloud computing clearly better for the environment? Yes -- more people using fewer high-powered servers saves energy. No -- cloud computing encourages more computer use generally, which increases demand for energy, an ...

1 explain why you agree or disagree with the following

1. Explain why you agree or disagree with the following statement: "A well-written survey can enhance response rates." 2. What are the crucial issues affecting the customer landscape ? which shifts are underway ? where i ...

Make a powerpoint presentationcompany wal mart company1

Make a Powerpoint Presentation Company: Wal Mart Company 1. Strategy of WAL-MART COMPANY 2. Using Deal and Kennedy’s or Handy’s classification discuss the organizational culture prevalent in WAL-MART company and provide ...

Sales amp operational planning flynn commercial freezer ltd

Sales & Operational Planning, Flynn Commercial Freezer Ltd. (FCF Ltd), makes commercial and industrial freezers (the kind hotels and restaurants use, and has the aggregate demand requirements for the next six months as g ...

1 in relation to the parts of the human resources

1. In relation to the parts of the human resources management process, labor relations would fall under __________. a. human resources planning b. attracting employees c. developing employees d. retaining employees 2. In ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year