Software Development Specialists (SDS) is involved with developing software for customers in the banking industry. SDS breaks a large programming project into teams that perform the necessary steps. Team A is responsible for going from general systems design all the way through to actual systems testing. This involves 18 separate activities. Team B is then responsible for the final installation. To determine cost and time factors, optimistic, most likely, and pessimistic time estimates have been made for all of the 18 activities involved for team A. The first step that this team performs is general systems design. The optimistic, most likely, and pessimistic times are 3, 4, and 5 weeks. Following this, a number of activities can begin. Activity 2 is involved with procedures design. Optimistic, most likely, and pessimistic times for completing this activity are 4, 5, and 12 weeks. Activity 3 is developing detailed report designs. Optimistic, most likely, and pessimistic time estimates are 6, 8, and 10 weeks. Activity 4, detailed forms design, has optimistic, most likely, and pessimistic time estimates of 2, 5, and 5 weeks.

Activities 5 and 6 involve writing detailed program specifications and developing file specifications. The three time estimates for activity 5 are 6, 7, and 8 weeks, and the three time estimates for activity 6 are 3, 4, and 5 weeks. Activity 7 involves specifying system test data. Before this is done, activity 6, involving file specifications, must be completed. The time estimates for activity 7 are 2, 3, and 7 weeks. Activity 8 involves reviewing forms. Before activity 8 can be conducted, detailed forms design must be completed. The time estimates for activity 8 are 3, 3, and 9 weeks. The next activity, activity 9, is reviewing the detailed report design. This requires that the detailed report design, activity 3, be completed first. The time estimates for activity 9 are 1, 3, and 5 weeks, respectively. Activity 10 involves reviewing procedures design. Time estimates are 1, 2, and 9 weeks. Of course, procedures design must be done before activity 10 can be started. Activity 11 involves the system design checkpoint review. A number of activities must be completed before this is done. These activities include reviewing the forms, reviewing the detailed report design, reviewing the procedures design, writing detailed program specs, and specifying system test data. The optimistic, most likely, and pessimistic time estimates for activity 11 are 3, 4, and 5 weeks. Performing program logic design is activity 12. This can be started only after the system design checkpoint review is completed. The time estimates for activity 12 are 4, 5, and 6 weeks.

Activity 13, coding the programs, is done only after the program logic design is completed. The time estimates for this activity are 6, 10, and 14 weeks. Activity 14 is involved in developing test programs. Activity 13 is the immediate predecessor. Time estimates for activity 14 are 3, 4, and 11 weeks. Developing a system test plan is activity 15. A number of activities must be completed before activity 15 can be started. These activities include specifying system test data, writing detailed program specifications, and reviewing procedure designs, the detailed report design, and forms. The time estimates for activity 15 are 3, 4, and 5 weeks. Activity 16, creating system test data, has time estimates of 2, 4, and 6 weeks. Activity 15 must be done before activity 16 can be started. Activity 17 is reviewing program test results. The immediate predecessor to activity 17 is to test the programs (activity 14). The three time estimates for activity 17 are 2, 3, and 4 weeks. The final activity is conducting system tests. This is activity 18. Before activity 18 can be started, activities 16 and 17 must be complete. The three time estimates for conducting these system tests are 2, 6, and 7 weeks. How long will it take for team A to complete its programming assignment?

Business Management, Management Studies

  • Category:- Business Management
  • Reference No.:- M93063070

Have any Question?


Related Questions in Business Management

Name a company that addressed a recent ethical problem in a

Name a company that addressed a recent ethical problem in a positive way. Also, explain how or if this positively affects us as a community?

When it is appropriate to use the trade-off process what

When it is appropriate to use the trade-off process. What conditions apply, and the technical evaluation criteria that might be used?

Need help with a essay with the following phrase for

Need help with a essay with the following phrase for analyzing : " Capitalism is at the heart of how people and organisations are managed in contemporary society" May i ask for a better explanation of the question? Also ...

How could these three tenets of the auburn creed be used to

How could these three tenets of the Auburn Creed be used to motivate others: "I believe that this is a practical word and that I can count only on what I earn. Therefore, I believe in work, hard work." "I believe in educ ...

How can these two tenets of the auburn creed by used in

How can these two tenets of the Auburn Creed by used in addressing teamwork issues: "I believe in honesty and truthfulness, without which I cannot win the respect and confidence of my fellow men." "I believe in the human ...

Discuss the advantages of having and interacting in a

Discuss the advantages of having and interacting in a diverse workplace. Consider the wide range of ideas and perspectives that a range of team members bring to a team, that are of differing ages, ethnic backgrounds and ...

Parmigiano-reggiano global recognition of geographical

Parmigiano-Reggiano: Global Recognition of Geographical Indications What historical factors have helped support the consortium's claims for the geographic specificity of Parmigiano-Reggiano and Parmesan? What are the eco ...

Communication planthis communication plan will be a roadmap

Communication Plan This communication plan will be a roadmap on how the new division will best be able to communicate with Biotech's corporate headquarters, suppliers, other divisions, and internally. This should lay out ...

Discuss strategies to obtain feedback from a customer and

Discuss strategies to obtain feedback from a customer and clients when working in sales.

Describe different networking methods and the advantages

Describe different networking methods and the advantages and disadvantages of them?

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As