Q. Shirley Hopkins is developing a program in leadership training for middle managers. Shirley has listed a number of activities which must be completed before a training program of this nature could be conducted. Activities, immediate predecessors, also times appear in accompanying table.
Activity Immediate Predecessor Time (Days)
A - 2
B - 5
C - 1
D B 10
E A,D 3
F C 6
G E,F 8
a. Develop an AON network for this problem.
b. Illustrate what is critical path?
c. Illustrate what is total project completion time?
d. Illustrate what is slack time for each individual activity?