Q. Get step by step solution to this homework question now:
Shirley Hopkins is developing a program in leadership training for middle managers. Shirley has listed a number of activities that must be completed before a training program of this nature could be conducted. Activities, immediate predecessors and times appear in acbusinessing table.
Activity Immediate Predecessor Time (Days)
A - 2
B - 5
C - 1
D B 10
E A,D 3
F C 6
G E,F 8
a. Develop an AON ne2rk for this problem.
b. Illustrate what is critical path?
c. Illustrate what is total project completion time?
d. Illustrate what is slack time for each individual activity?