For an organization, the following project schedule is given. Assume that all times are in days.

Task Predecessor Normal Time Crash Time Crash Cost Slope
A None 7 7 NA
B A 3 3 NA
C A 8 4 600
D A 4 4 NA
E B 6 5 600
F C, D 2 2 NA
G E, F 6 6 NA
H F 5 3 400
I G, H 4 4 NA
J I 2 2 NA

In a 3- to 4-page Microsoft Word document, address the following:

  • Draw the AON project network using Microsoft Project, Microsoft Visio, or some other tool capable of creating such a network. Perform a critical path analysis for the network and calculate the ES, EF, LS, and LF times.
  • Calculate the slack time for each activity.
  • Identify the critical path.
  • Assume that the organization will receive a $400 bonus for each day the duration of the project is shortened. The organization is also responsible for paying the crash cost associated with shortening the schedule. To maximize the net profit, identify which task you should crash and by how much.

Support your responses with examples.

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M91379898
  • Price:- $30

Guranteed 24 Hours Delivery, In Price:- $30

Have any Question?


Related Questions in Operation Management

The article as a synopsis is about crisis management though

The article as a synopsis is about crisis management. Though to go a bit further, it is also not only about managing a crisis, but attempting to plan as well as possible to avoid crisis. You cannot plan for everything, s ...

1 when if ever is an employee justified in blowing the

1. When, if ever, is an employee justified in blowing the whistle? What do you see as the most important factors that he or she needs to consider in deciding whether to blow the whistle? 2. Compare the internal and exter ...

Rocky mountain tire center sells 9000 go-cart tires per

Rocky Mountain Tire Center sells 9,000 go-cart tires per year. The ordering cost for each order is $40, and the holding cost is 50% of the purchace price of the tires per year. The purchase price is $24 per tire if fewer ...

According to the text managing productivity and performance

According to the text, managing productivity and performance are important for operational managers to ensure that their operations are becoming more cost effective and efficient over time. Principles of healthcare opera ...

1 how should mcdonaldrsquos respond when ads promoting

1. How should McDonald’s respond when ads promoting healthy lifestyles featuring Ronald McDonald are equated with Joe Camel and cigarette ads? Should McDonald’s eliminate Ronald McDonald in its ads? 2. Discuss the merits ...

Develop a minimum 500-word analysis of the international

Develop a minimum 500-word analysis of the international economy in which you do the following: SEE ATTACHED Research each country, using resources such as the CIA World Fact Book, World Bank data, World Trade Organizati ...

Choose one of the following three discussion topics your

Choose ONE of the following three discussion topics. Your paper should be 250-300 words and APA formatted. 1. Analyze the concept of "best practices" and how its implementation impacts competitive advantage. 2. Analyze t ...

1 there are many decision-making biases that can influence

1. There are many decision-making biases that can influence a manager's decision. Which bias do you believe is the most common one? Give examples. 2. According to John Boatright, what is right, and what is wrong, about s ...

Lsquorelationship sellingrsquo can be described as a

‘Relationship Selling’ can be described as a central goal focused on securing, building, and maintaining long-term relationships with profitable customers. According to our reading assignment this week, professional sale ...

Javier drops in on his friend luiz to see how his first

Javier drops in on his friend Luiz to see how his first project management assignment is going. Luiz had just finished the defining and organizing phase and presented his plan to project stakeholders. In his plan, he dre ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As