Schedule the following activities using CPM:
Activity Immed. Precessor time (weeks)
A 1
B A 4
C A 3
D B 2
E C, D 5
F D 2
G F 2
H E, G 3
a. Draw the network.
b. What is the critical path?
c. How many weeks will it take to complete the project?
d. Which activities have slack, and how much?