Scenario

Your organization has just completed the Initiation Process for implementing an Email System Upgrade. It was identified in a recent meeting with management leaders from the Sales, Consulting and IT departments that the current email system is causing significant amount of business interruptions and must be updated immediately. You have been assigned the role of project manager to develop the project schedule and budget. As project manager, you are responsible for implementing and enforcing the project schedule and its estimates, expected costs, and the techniques and methods that will be chosen to execute and control the project. The project is being initiated with the following initial project scope in mind:

  • There are five email systems currently being used across twelve departments and offices. These will be replaced and consolidated into one email system.
  • New Email Standards and Protocols will be established and training provided to all departments.
  • All 2000 current email users will be converted to the new system, and 500 new users that did not have email before will be added.
  • Users will have both LAN and remote access to email.
  • Help desk and support infrastructure will be set-up to accommodate the new system.
  • Equipment will be salvaged.

User PCs will be upgraded to accommodate the new email system.

Your first presentation was excellent, and the project work is moving forward. No project can be managed without a WBS. The CIO now has decided that it is time for you to create the work breakdown structure (WBS) for the project.

  • Determine the following:
    • The scope of the project
    • How is the WBS created? Do you use the PMBOK® Guide project life cycle phases (initiating, planning, executing, monitoring and control, and close out) as the noun or do you use the deliverable or project name as the noun? The noun in a WBS is the deliverable.
    • The work breakdown structure (WBS) that is representative of the project scope, which should include the following:
      • Deliverables/Outputs
      • Activities
      • Tasks
      • Products or services
  • All major tasks should be organized into work packages. A work-package is the lowest level of the WBS.
  • Do not decide on estimates for the activities or work-packages at this time.
  • This determining WBS essentials should be between 150-200 words.
  • Part 2
  • Now that you have had the opportunity to discuss your project and somewhat build your WBS in the group discussion area and offline, use MS project software to complete the following:
  • Creating your WBS in MS Project. Using MS Project, enter all the WBS deliverables/outputs, activities, and tasks into a new MS Project file and save it with your group name and course #.
  • Sequence your activities. Now that you have defined your activities, ensure that they are listed in the order that they should be completed. If one activity is dependent on another, be sure to list that dependency in the "Predecessor" column.
  • Activity estimation. Assign an initial work effort to each of the activities from the WBS.
  • Provide an estimation framework for the WBS. This should be approximate. You're allowed to make assumptions as long you're being realistic.
  • The framework should be estimated in days.
  • Duration estimation. Now that you have defined the WBS activities, sequenced them in a logical order and defined the dependency relationships between them, and estimated resources, add the activity duration for all activities then add a start date to each task. The finish date should automatically populate. If you have a conflict, review your predecessor relationships. Remember, you do not need to add anything to the summary tasks (the deliverable/output). The summary tasks will update automatically as soon as you link the activities to them. They summarize the duration and start/finish date for that entire deliverable. The screen shot below should provide you with an example of how your work will look before submitting this assignment. Many more examples are available in the Project Management Homepage in the Learning Center.
  • Assign resources. In the resource name column in your MS Project file, add a resource name to each task. You may use hypothetical names or your group's names.
    • There is no length to how many tasks your WBS should be made up of, but it should be long enough to convince your CIO at a glance that this is all the work that needs to be completed for this project. Ideally, you shouldn't have less than 50 tasks. You can organize your tasks however you choose to use the noun. It is recommended that you use the PMBOK® Guide project management phases to organize your WBS.

Part 3

  • Based on your deliverable (Part 1)
    • Apply the standard PERT estimating formula and calculate the expected estimate (Te) for each activity.
      • Use the table attached to complete the estimates.
  • Explain the purpose behind the PERT calculations.
    • PERT estimate calculations and your explanation of them should be between 550-700 words.

Business Management, Management Studies

  • Category:- Business Management
  • Reference No.:- M93086690

Have any Question?


Related Questions in Business Management

Name a company that addressed a recent ethical problem in a

Name a company that addressed a recent ethical problem in a positive way. Also, explain how or if this positively affects us as a community?

When it is appropriate to use the trade-off process what

When it is appropriate to use the trade-off process. What conditions apply, and the technical evaluation criteria that might be used?

Need help with a essay with the following phrase for

Need help with a essay with the following phrase for analyzing : " Capitalism is at the heart of how people and organisations are managed in contemporary society" May i ask for a better explanation of the question? Also ...

How could these three tenets of the auburn creed be used to

How could these three tenets of the Auburn Creed be used to motivate others: "I believe that this is a practical word and that I can count only on what I earn. Therefore, I believe in work, hard work." "I believe in educ ...

How can these two tenets of the auburn creed by used in

How can these two tenets of the Auburn Creed by used in addressing teamwork issues: "I believe in honesty and truthfulness, without which I cannot win the respect and confidence of my fellow men." "I believe in the human ...

Discuss the advantages of having and interacting in a

Discuss the advantages of having and interacting in a diverse workplace. Consider the wide range of ideas and perspectives that a range of team members bring to a team, that are of differing ages, ethnic backgrounds and ...

Parmigiano-reggiano global recognition of geographical

Parmigiano-Reggiano: Global Recognition of Geographical Indications What historical factors have helped support the consortium's claims for the geographic specificity of Parmigiano-Reggiano and Parmesan? What are the eco ...

Communication planthis communication plan will be a roadmap

Communication Plan This communication plan will be a roadmap on how the new division will best be able to communicate with Biotech's corporate headquarters, suppliers, other divisions, and internally. This should lay out ...

Discuss strategies to obtain feedback from a customer and

Discuss strategies to obtain feedback from a customer and clients when working in sales.

Describe different networking methods and the advantages

Describe different networking methods and the advantages and disadvantages of them?

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As