Q. Robert- Peter is developing a program in leadership training for middle level managers of Peter Holding. Robert has listed a number of activities which must be completed before a training program of this nature could be conducted. The activities, immediate predecessors also times appear in the accompany table.
Activity Immediate Pred. Time (days)
A - 2
B - 5
C - 1
D B 10
E A, D 3
F C 6
G E,F 8
a. Develop an AON network for this problem
b. Illustrate what is the critical path?
c. Illustrate what is the total completion time?
d. Illustrate what is the slack time for each activity?