Relating with project management, can you please show how to draw an AOA (Activity on Arrow) diagram assuming a Finish-Start relationship for the following activities?
Activity Duration Predecessor
A 70 days -
B 30 days A
C 70 days B
D 120 days A
E 120 day D
F 120 days B, E
G 90 days B, E
H 120 day B, E
I 140 day F, H
J 90 days F, H
K 30 days F, H
L 120 days F, H
M 75 days I
N 30 days M
O 90 days E
P 180 days O
Q 90 days O
R 90 days P, Q
S 20 days G,J,L,N,R