Question: Dimwit has refused to issue Change Orders for other work, claimed to be "extra" by Wackinsmack. Included in the pile of refused change orders, are two "Field Directives" issued by Dimwit's Engineer (Ithinkican Engineering Consultants, Inc.) which the Owner feels are not changes; a claim for Differing Site Conditions, which Dimit says Wackinsmack should have known about; and, the discovery of hazardous "contamination" in the excess excavated soil materials which had to be trucked off the site and disposed of (which Dimwit feels is Wackinsmack's contractual responsibility).

The accumulation of changes, including those for which Dimwit has not agreed, has resulted in delays to the project. Wackinsmack failed to achieve Substantial Completion of the work by the Contract End Date (as adjusted by approved change orders). As a result Dimwit has assessed liquidated damages against Wackinsmack for late completion. Wackinsmack has, in turn, assessed Acme for 53% of the liquidated damages based on Acme's proportionate share of the prime contract price.

One of the disputed Work Orders involves the direction by Ithinkican to relocate some of the process piping (work performed by Acme) to avoid conflicts with other aspects of the design. Ithinkican has advised Dimwit that this work was part of the contractor's "methods and means" responsibility and is not an extra. Acme performed the work and claims $350,000 in extra costs.

Assumption: Assume that, as a result of all of the changes, including the disputed work order, the project has been delayed by 200 calendar days. If the Contract End Date were to be enlarged by 200 calendar days, the project would have been completed on time, and there would be no basis for Dimwit to assess liquidated damages.

Essay Assignment: Please prepare a letter to Dimwit asserting Wackinsmack's view that it is entitled to an excused, compensable delay and enlargement of the Contract End Date, and that Dimwit should rescind its assessment of liquidated damages.

Homework Help/Study Tips, Others

  • Category:- Homework Help/Study Tips
  • Reference No.:- M92694487

Have any Question?


Related Questions in Homework Help/Study Tips

Review the website airmail service from the smithsonian

Review the website Airmail Service from the Smithsonian National Postal Museum that is dedicated to the history of the U.S. Air Mail Service. Go to the Airmail in America link and explore the additional tabs along the le ...

Read the article frank whittle and the race for the jet

Read the article Frank Whittle and the Race for the Jet from "Historynet" describing the historical influences of Sir Frank Whittle and his early work contributions to jet engine technologies. Prepare a presentation high ...

Overviewnow that we have had an introduction to the context

Overview Now that we have had an introduction to the context of Jesus' life and an overview of the Biblical gospels, we are now ready to take a look at the earliest gospel written about Jesus - the Gospel of Mark. In thi ...

Fitness projectstudents will design and implement a six

Fitness Project Students will design and implement a six week long fitness program for a family member, friend or co-worker. The fitness program will be based on concepts discussed in class. Students will provide justifi ...

Read grand canyon collision - the greatest commercial air

Read Grand Canyon Collision - The greatest commercial air tragedy of its day! from doney, which details the circumstances surrounding one of the most prolific aircraft accidents of all time-the June 1956 mid-air collisio ...

Qestion anti-trustprior to completing the assignment

Question: Anti-Trust Prior to completing the assignment, review Chapter 4 of your course text. You are a manager with 5 years of experience and need to write a report for senior management on how your firm can avoid the ...

Question how has the patient and affordable care act of

Question: How has the Patient and Affordable Care Act of 2010 (the "Health Care Reform Act") reshaped financial arrangements between hospitals, physicians, and other providers with Medicare making a single payment for al ...

Plate tectonicsthe learning objectives for chapter 2 and

Plate Tectonics The Learning Objectives for Chapter 2 and this web quest is to learn about and become familiar with: Plate Boundary Types Plate Boundary Interactions Plate Tectonic Map of the World Past Plate Movement an ...

Question critical case for billing amp codingcomplete the

Question: Critical Case for Billing & Coding Complete the Critical Case for Billing & Coding simulation within the LearnScape platform. You will need to create a single Microsoft Word file and save it to your computer. A ...

Review the cba provided in the resources section between

Review the CBA provided in the resources section between the Trustees of Columbia University and Local 2110 International Union of Technical, Office, and Professional Workers. Describe how this is similar to a "contract" ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As