QUESTION 1

Read the article below and answer the questions that follow.

Brian Smith, network administrator at Advanced Energy Technology (AET), has been given the responsibility of implementing the migration of a large data centre to a new office location. Careful planning is needed because AET operates in the highly competitive petroleum industry. AET is one of five national software companies that provide an accounting and business management package for oil jobbers and gasoline distributors. A few years ago, AET jumped into the °application service provider" world. Their large data centre provides clients with remote access to AET's complete suite of application software systems. Traditionally, one of AET's primary competitive advantages has been the company's trademarks IT reliability. Due to the complexity of this project, Brian will have to use a parallel method of implementation. Although this will increase project costs, a parallel approach is essential if reliability is not to be compromised.

Currently, AET's data centre is located on the second floor of a renovated old bank building in downtown Corvallis, Oregon. The company is moving to a new, one-level building located in the recently developed industrial complex at the Corvallis International Airport. On February 1, Brian is formally assigned the task by the Vice-President of Operations, Dan Whitmore, with the following guidelines:

- From start to finish, it is anticipated the entire project will take three to four months to complete.
- It is essential that AET's 235 clients suffer no downtime.

Whitmore advises Brian to come back to the Executive Committee on February 15, with a presentation on the scope of the project that includes costs, "first-cut" timeline, and proposed project team members. Brian had some preliminary discussions with some of AET's managers and directors from each of the functional departments and then arranged for a full-day scope meeting on February 4 with a few of the managers and technical representatives from operations, systems, facilities, and applications. The scope team determined the following:

- Three to four months is a feasible project timeline and first-cut cost estimate is $80,000 - $90,000 (this includes the infrastructure upgrade of the new site).
- Critical to the "no-downtime" requirement is the need to completely rely on AET's remote disaster recovery "hot" site for full functionality.
- Brian will serve as project manager of a team consisting of one team member each from facilities, operations/systems, operations/telecommunications, systems & applications, and customer service.

Brian's Executive Committee report was positively received and, after a few modifications and recommendations, he was formally charged with responsibility for the project. Brian recruited his team and scheduled their first team meeting (March 1) as the initial task of his project planning process.

Once the initial meeting is conducted Brian can hire the contractors to renovate the new data centre. During this time Brian will figure out how to design the network. Brian estimates that screening and hiring a contractor will take about one week and that the network will take about two weeks. The new centre requires a new ventilation system. The manufacturer's requirements include an ambient temperature of 67 degrees to keep all of the data servers running at optimal speeds. The ventilation system has a lead-time of three weeks. Brian will also need to order new racks to hold the servers, switches and other network devices. The racks have a two-week delivery time.

The data centre supervisor requested that Brian replace all of the old power supplies and data cables. Brian will need to order these as well. Because Brian has a great relationship with the vendor, they guarantee that it will take only one week lead time for the power supplies and the data cables. Once the new ventilation system and racks arrive, Brian can begin installing them. It will take one week to install the ventilation system and three weeks to install the racks. The renovation of the new data centre can begin as soon as the contractors have been hired. The contractors tell Brian that construction will take 20 days. Once the construction begins and before Brian installs the ventilation system and racks, the city inspector must approve the construction of the raised floor.

The city inspector will take two days to approve the infrastructure. After the city inspection and after the new supplies and cables have arrived, Brian can install the power supplies and run the cables. Brian estimates that it will take five days to install the power and one week to run all of the data cables. Before Brian can assign an actual date for taking the network off line and switching to the hot remote site, he must get approval from each of the functional units ("Switchover Approval").

Meetings with each of the functional units will require one week. During this time, he can initiate a power check to ensure that each of the tracks has sufficient voltage. This will require only one day.

Upon completion of the power check, he can take one week to install his test servers. The test servers will test all of the primary network functions and act as a safeguard before the network is taken off line. The batteries must be charged; ventilation installed, and test servers up and running before management can be assured that the new infrastructure is safe, which will take two days. Then they will sign off the Primary Systems check, taking one day of intense meetings. They will also set an official date for the network move.

Brian is happy that everything has gone well thus far and is convinced that the move will go just as smoothly. Now that an official date is set, the network will be shut down for a day. Brian must move all of the network components to the new data centre. Brian will do the move over the weekend - two days - when user traffic is at low point.

1.1 Develop a WBS for this project
1.2 Discuss the five approaches that Brian can use to develop a WBS that Brian can use. Which approach would you recommend?

QUESTION 2

The table below gives the duration estimates in days for a construction projection.

Activity

A

Predecessor

-

Optimistic

Most Likely

Pessimistic

 

B

-

1

3

6

C

-

3

5

8

D

A

9

11

20

E

A

2

5

7

F

B

6

9

20

G

C

5

10

22

H

E, F

3

5

12

I

D

4

7

9

J

G

6

9

13

K

H,J

3

4

6

L

I,K

7

10

23

2.1 Determine the expected completion time for each activity. Round off answers to the nearest whole number

2.2 Construct an AON network for the activities of this contract.

2.3 Determine the critical path for the project by calculating the slack for each activity.

QUESTION 3

With the aid of an example, critically discuss how performing activities in parallel may accelerate project duration.

Assignment Guidelines

- The length of your answers to each question should be in line with the mark allocation
- Your assignment should include a table of contents page
- Text: Font: Arial or Times New Roman size 12; Line spacing: 1.5
- All text must be justified at each margin
- Your answers must include any theories, charts, tables or exhibits necessary to support your analysis and recommendations
- Ensure that readings are not merely reproduced without original critical comments and views. Cohesive and logical arguments reflecting original thinking are encouraged
- References: At least 4 sources of references (textbooks, journals, press reports, intemet articles, etc.) must be utilised in the body of your assignment. All sources must be appropriately listed under your Bibliography. Harvard system of referencing to be used. Students will be penalised up to 10% for incorrect or no referencing.

Homework Help/Study Tips, Others

  • Category:- Homework Help/Study Tips
  • Reference No.:- M92848847
  • Price:- $150

Guranteed 48 Hours Delivery, In Price:- $150

Have any Question?


Related Questions in Homework Help/Study Tips

Review the website airmail service from the smithsonian

Review the website Airmail Service from the Smithsonian National Postal Museum that is dedicated to the history of the U.S. Air Mail Service. Go to the Airmail in America link and explore the additional tabs along the le ...

Read the article frank whittle and the race for the jet

Read the article Frank Whittle and the Race for the Jet from "Historynet" describing the historical influences of Sir Frank Whittle and his early work contributions to jet engine technologies. Prepare a presentation high ...

Overviewnow that we have had an introduction to the context

Overview Now that we have had an introduction to the context of Jesus' life and an overview of the Biblical gospels, we are now ready to take a look at the earliest gospel written about Jesus - the Gospel of Mark. In thi ...

Fitness projectstudents will design and implement a six

Fitness Project Students will design and implement a six week long fitness program for a family member, friend or co-worker. The fitness program will be based on concepts discussed in class. Students will provide justifi ...

Read grand canyon collision - the greatest commercial air

Read Grand Canyon Collision - The greatest commercial air tragedy of its day! from doney, which details the circumstances surrounding one of the most prolific aircraft accidents of all time-the June 1956 mid-air collisio ...

Qestion anti-trustprior to completing the assignment

Question: Anti-Trust Prior to completing the assignment, review Chapter 4 of your course text. You are a manager with 5 years of experience and need to write a report for senior management on how your firm can avoid the ...

Question how has the patient and affordable care act of

Question: How has the Patient and Affordable Care Act of 2010 (the "Health Care Reform Act") reshaped financial arrangements between hospitals, physicians, and other providers with Medicare making a single payment for al ...

Plate tectonicsthe learning objectives for chapter 2 and

Plate Tectonics The Learning Objectives for Chapter 2 and this web quest is to learn about and become familiar with: Plate Boundary Types Plate Boundary Interactions Plate Tectonic Map of the World Past Plate Movement an ...

Question critical case for billing amp codingcomplete the

Question: Critical Case for Billing & Coding Complete the Critical Case for Billing & Coding simulation within the LearnScape platform. You will need to create a single Microsoft Word file and save it to your computer. A ...

Review the cba provided in the resources section between

Review the CBA provided in the resources section between the Trustees of Columbia University and Local 2110 International Union of Technical, Office, and Professional Workers. Describe how this is similar to a "contract" ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As