Question 1.1.

In a PERT network, the earliest (activity) start time is the

earliest time that an activity can be finished without delaying the entire project.

latest time that an activity can be started without delaying the entire project.

earliest time that an activity can start without violation of precedence requirements.

latest time that an activity can be finished without delaying the entire project.

None of the above

Question 2.2.

PERT and CPM are quantitative analysis tools designed to schedule and control large projects.

True

False

Question 3.3.

The expected time in PERT is

a weighted average of the most optimistic time, most pessimistic time, and four times the most likely time.

the modal time of a beta distribution.

a simple average of the most optimistic, most likely, and most pessimistic times.

the square root of the sum of the variances of the activities on the critical path.

None of the above

Question 4.4.

On a practical note - if we are using waiting line analysis to study customers calling a telephone number for service, balking is probably not an issue.

True

False

Question 5.5.

An arrival in a queue that reneges is one who

after joining the queue, becomes impatient and leaves.

refuses to join the queue because it is too long.

goes through the queue, but never returns.

jumps from one queue to another, trying to get through as quickly as possible.

None of the above

Question 6.6.

PERT was developed for a project for which activity or task times were uncertain.

True

False

Question 7.7.

The following represents a project with four activities. All times are in weeks.

Activity

Immediate

Predecessor

Optimistic

Time

Most

Likely

Time

Pessimistic

Time

A

-

2

8

14

B

-

8

8

8

C

A

6

9

18

D

B

5

11

17

According to the data in Table above, what is the minimum expected completion time for the project?

18

19

37

11

None of the above

Question 8.8.

A suburban specialty restaurant has developed a single drive-thru window. Customers order, pay, and pick up their food at the same window. Arrivals follow a Poisson distribution while service times follow an exponential distribution. If the average number of arrivals is 6 per hour and the service rate is 2 every 15 minutes, what is the average number of customers waiting in line behind the person being served?

0.50

0.75

2.25

3.00

None of the above

Question 9.9.

Given the following small project, the critical path is ________ days.

Activity

Immediate

Predecessor

Time

(days)

A

-

10

B

-

4

C

A, B

6

10

14

16

20

None of the above

Question 10.10.

The study of waiting lines is called queuing theory.

True

False

Question 11.11.

Slack is the time an activity can be delayed without impacting the completion time of the project.

True

False

Question 12.12.

CPM was developed for use in managing projects about which we have good information about activity or task completion times.

True

False

Question 13.13.

In queuing analysis, total expected cost is the sum of expected ________ plus expected ________.

service costs, arrival costs

facility costs, calling costs

calling cost, inventory costs

calling costs, waiting costs

service costs, waiting costs

Question 14.14.

One of the most significant benefits of PERT is that it forces the project manager to sit down and plan the project in great detail-and thus come to an understanding of relationships between the activities.

True

False

Question 15.15.

Given the following small project, the critical path is ________ days.

Activity

Immediate

Predecessor

Time

(days)

A

-

8

B

A

4

C

-

10

4

10

12

22

None of the above

Question 16.16.

A bank with a single queue to move customers to several tellers is an example of a single-channel system.

True

False

Question 17.17.

Slack time in a network is the

amount of time that an activity would take assuming very unfavorable conditions.

shortest amount of time that could be required to complete the activity.

amount of time that you would expect it would take to complete the activity.

difference between the expected completion time of the project using pessimistic times and the expected completion time of the project using optimistic times.

amount of time that an activity can be delayed without delaying the entire project.

Question 18.18.PERT is a deterministic analysis tool allowing for precise times of activities within a project.

True

False

Question 19.19.

Given an activity's optimistic, most likely, and pessimistic time estimates of 2, 5, and 14 days respectively, compute the PERT expected activity time for this activity.

6

7

9

5

None of the above

Question 20.20.

Frequently in queuing problems, the number of arrivals per unit of time can be estimated by a probability distribution known as the Poisson distribution.

True

False

Question 21.21.

The customer who arrives at a bank, sees a long line, and leaves to return another time is

balking.

cropping.

reneging.

blithering.

None of the above

Question 22.22.

A goal of many waiting line problems is to help a firm find the ideal level of services that minimize the cost of waiting and the cost of providing the service.

True

False

Question 23.23.

Lines at banks where customers wait for a teller window are usually representative of a

single-channel, multiphase system.

single-channel, single-phase system.

multichannel, multiphase system.

multichannel, single-phase system.

None of the above

Question 24.24.

One difficulty in waiting line analysis is that it is sometimes difficult to place a value on customer waiting time.

True

False

Question 25.25.

Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 6, and 14 days respectively, compute the PERT expected activity time for this activity.

8

6

7

9

None of the above

Homework Help/Study Tips, Others

  • Category:- Homework Help/Study Tips
  • Reference No.:- M92286788
  • Price:- $25

Priced at Now at $25, Verified Solution

Have any Question?


Related Questions in Homework Help/Study Tips

Assignment what major do you plan to pursue here we will do

Assignment: What major do you plan to pursue? Here we will do a mini example essay in class about the different careers you might be able to pursue with your degree. The essay should only be three paragraphs long, so it ...

Question conduct an internet search about the murder of

Question: Conduct an internet search about the murder of Yeardley Love. After researching the story, write a 500¬-750-word essay addressing the following. 1. Assuming there was abuse occurring prior to the death of Yeard ...

Question development of us health care in hospitals based

Question: "Development of U.S. Health Care in Hospitals Based on the Foundation of U.S. Law" Please respond to the following: • * From the scenario, relate the basic steps in the development of U.S. health law, leading u ...

Answer the following questions what are your thoughts on

Answer the following Questions : What are your thoughts on the various "fad diets" including: diet foods, high protein diets, and very low calorie diets. Do you feel these are more or less effective than to exercise and ...

Motivating students is something that all teachers must

Motivating students is something that all teachers must learn how to do and it can be done through the use of various forms of technology, instructional, and engagement strategies. It is crucial for all teachers to ident ...

Assignment -recoil affecting system performance - show the

Assignment - Recoil affecting system performance - Show the big efferent between fixed and free recoil on Muzzle velocity, it must just be discussed with a bit of detail. Refer to the table in the text. How a recoil syst ...

Briefly describe the neuronal regulation of sleep this

Briefly describe the neuronal regulation of sleep. ( this question must include a discussion of important brain regions, neurotransmitters, and/or sleeping disorders that support the role of the brain and nervous system ...

Question you are charged with the responsibility of

Question: You are charged with the responsibility of producing a response paper to a scenario facing Nairobi, Kenya. Please see the attached scenario, "Urbanization, Poverty, and the Basic Needs in Nairobi, Kenya" and in ...

Assignment tasks corporate regulationido you own research

ASSIGNMENT TASKS CORPORATE REGULATION (i) Do you own research and critically discuss whether the financial accounting and reporting should be regulated or manager should be allowed to disclose financial accounting inform ...

Assignment 4 essay peak performance in athletespart i

Assignment 4: Essay: Peak Performance In Athletes Part I: Imagine that you are the coach of an elite-level athlete in training for the upcoming Olympic Games. Create a hypothetical athlete in a sport of your choice. Disc ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As