Question 1 of 17

At a Six Sigma quality level, if the process mean isheld exactly on target, the expected result would be:

A. 1.5 defects per thousand opportunities.

B. 2.8 defects per ten thousand opportunities.

C. 3.4 defects per million opportunities.

D. 2.0 defects per billion opportunities.

 

Question 2 of 17

A grocery store finds that a patron typicallypurchases 20 items per visit. In one day, the grocer found that the checkoutscanners made 240 price-reading errors in servicing 11,000 patrons. The dpmo is_____.

 A. 0.022

 B. 45.83

 C. 1091

 D. 1818

 

Question 3 of 17

Which of the following constitutes an operationaldefinition of a service quality measure?

 A. Highlyprofessional service

 B. Few latedeliveries

C. Phone calls answered within two rings

D. Very accurate customer billing

 

 Question 4 of17

A level of 3.4 defects per million opportunities canbe achieved in all of the following ways EXCEPT:

A. with 0.0-sigma off-centering and 4.0-sigma quality.

B. with 0.5-sigma off-centering and 5.0-sigma quality.

C. with 1.0-sigma off-centering and 5.5-sigma quality.

D. with 1.5-sigma off-centering and 6.0-sigma quality.

 

Question 5 of 17

A _____ is a _____ of the data from the largestfrequency to the smallest.

A. histogram; scatter diagram

B. pareto diagram; histogram

C. scatter diagram; break-down chart

D. check sheet; chronological chart

 

Question 6 of 17

Control limits relate to _____, while specificationlimits relate to individual measurements.

A. values within the upper and lower control limits

B. total values in the range

C. median values

D. averages of samples

 

Question 7 of 17

A manager at a canning company wants to monitor thenumber of orange

juice cans it produces each day that are beyond theupper specification

limit for can diameter. Each day an employee willrandomly select 150

cans and then determine and plot the number of cansthat are beyond the

upper specification limit for can diameter. Theappropriate control

chart is a(n):

A. -chart.

B. R-chart.

C. p-chart.

D. np-chart.

 

Question 8 of 17

A run of __________ consecutive points on the sameside of the center line is evidence that the mean has shifted.

 A. four

 B. five

C. six

D. seven

E. eight

 

Question 9 of 17

Which of the following would be used to monitor thenumber of nonconforming items?

A. np-chart

B. p-chart

C. u-chart

D. n-chart

 

Question 10 of 17

Which of the following charts is used to monitor theaverage number of defects per unit when subgroup sizes vary?

 A. s-chart

B. c-chart

C. p-chart

D. u-chart

 

Question 11 of 17

If the sample size in a p-chart increases from 100 to120, the upper and lower control limits will

A. move farther apart away from the center line

B. move closer together toward the center line

C. remain the same distance from each other

D. both shift upward with the upper control limitmoving further from the center line and the lower control limit moving closerto the center line

Question 12 of 17

Five samples of size 20 were collected for a variablemeasurement. All sample data were greater than or equal to 3.0. The samplemeans and sample ranges are provided in the following table.

 

sample number

1

2

3

4

5

sample mean

5.0

4.9

5.0

6.0

5.2

sample range

0.2

4.9

0.1

0.0

0.3

The values of which sample are identical?

A. sample 1

B. sample 2

C. sample 3

D. sample 4

E. sample 5

 

Question 13 of 17

Twenty samples of size 50 were taken from a process.The total number of defectives found was 86. The standard deviation for thenumber of nonconforming items for an np-chart is:

 A. 0.0396

 B. 1.2538

 C. 1.9825

D. 2.0736

E. 3.9302

 

Question 14 of 17

The Chair of the Management Department at UB wants toconstruct a p-chart for determining whether the four (4) faculty membersteaching the course are under control with regards to the number of studentswho fail in the course. Accordingly, the Chair sampled 100 final grades fromlast year for each instructor, and computed the proportion of failures perinstructor as 0.03, 0.02, 0, and 0.03 respectively. The three sigma uppercontrol limit (UCL) would be

 A. 0.95

B. 0.062

C. 0.0388

D. 0.140

E. None of the above

 

Question 15 of 17

The control limits for a c-chart are:

Upper Control Limit = 10.00

Center Line = 4.00

Lower Control Limit = 0.00

 Determine thenumber of samples used to construct this chart.

A. 2

B. 4

C. 10

D. 16

E. Cannot be determined based on the informationpresented.

 

Question 16 of 17

Twenty-five circuit boards were inspected to determinethe total number of defects per unit. The total number of defects found was225. The standard deviation for use in designing the control limits for thec-chart is:

A. 3

B. 5

C. 9

D. 15

E. none of the above

 

Question 17 of 17

A machined part has a lower tolerance limit of 4.1inches and an upper tolerance limit of 4.9 inches. The range for thepre-control green zone is:

A. 4.1 to 4.9 inches.

B. 4.3 inches to 4.7 inches

C. 4.0 inches to 5.0 inches

D. less than 4.1 inches.

E. 4.5 inches to 4.9 inches.

 

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M91265082

Have any Question?


Related Questions in Operation Management

Conflictdefine functional versus dysfunctional conflict in

Conflict Define functional versus dysfunctional conflict in a work group and explain how you can increase functional conflict and decrease dysfunctional conflict. Develop a response that includes examples and evidence to ...

For this assignment you will need to find 2 articles in

For this assignment, you will need to find 2 articles in business that can help describe what are IT strategic initiative being undertaken by an organization are like. Choose a different organization for each of the arti ...

Coping with problems joe is a little nervous he has just

Coping With Problems Joe is a little nervous. He has just been transferred from another plant to take over a production line. Production is down and there is a serious problem with absenteeism. To make matters worse, the ...

Over 30 years ago michael porter identified a holistic

Over 30 years ago Michael Porter identified a holistic approach to understanding how competitive forces shape strategy. He posited that the only way to truly insulate an organization from underlying economic volatility i ...

You are the contracting officer for an air-to-ground

You are the contracting officer for an air-to-ground missile development program. A contract for pre-production models of the missile was awarded by your predecessor and the contractor is behind schedule. In a program me ...

The ikea case provides an excellent opportunity to apply

The IKEA case provides an excellent opportunity to apply strategic management concepts to a large privately-held company that is expanding into India. IKEA is a Netherlands-based Swedish company with a presence in 44 cou ...

Can you answer for me the following questions about social

Can you answer for me the following questions about social loafing and the three main causes of free-riding. 1. Give a description of the phenomenon of social loafing. 2. Give a description of the phenomenon of free-ridi ...

1 analyzing the bridgestonefirestone and ford motor company

1. Analyzing the Bridgestone/Firestone and Ford motor company, is it sufficient to use the ISO/QS 9000 standards as the main basis of vendor/product selection? 2. What position to these cars company ( 1. Volkswagen, 2. F ...

Research the effect of primary and secondary seat belt laws

Research the effect of primary and secondary seat belt laws on the occurrence of motor-vehicle injuries and fatalities. Explain how epidemiologic studies influenced the development of current seat belt laws. Describe how ...

Please provide a brief paragrap of the key takaways from

Please provide a brief paragrap of the key takaways from each of the following topics: Designing Clear Visuals in business reports Designing Successful Documents and Websites Writing Winning Proposals

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As