Ask Operation Management Expert

Question 1. For CPM with Three Activity Time estimates, what is the "Expected Time if the optimistic task completion time is 2 weeks, the most likely time is 4 weeks, and the pessimistic time is 12 weeks?

a) 7 weeks
b) 6 weeks
c) 5.33 weeks
d) 5 weeks
e) 4.5 weeks

Question 2. What is a problem that you can have using a Gantt chart to plan your project that is easy to rectify using CPM?

a) Interrelationships extremely difficult to visualize and work with for projects with less than 25 activities
b) All answers applym

c) Not very useful for major projects
d) Software not readily available to facilitate its use
e) No direct procedure for determining the critical path

Question 3. What is the difference between being a good Manager versus being a good Leader when directing a Project team?

a) Managers are in charge of leaders.
b) Good leaders usually make poor managers
c) Leaders tend to be effective while managers tend to be efficient
d) Managers tend to treat people as "people" while leaders tend to treat people as "tools."
e) Managers are good leaders

Question 4. What is the most significant problem with the Matrix project structure?

a) Too many bosses
b) Independent of project manager's negotiating skills
c) No potential for suboptimization
d) The project manager is responsible
e) Functional home for team members Save

Question 5. When using CPM with Three Activity Time estimates, how do you calculate "expected time?"

a) do a weighted average where the most likely time is weighted by 4 as compared to the optimistic and pessimistic time
b) average the optimistic, most likely, and pessimistic times
c) sum the optimistic and pessimistic times and divide by 2
d) No answer shown is correct
e) most likely time plus or minus variance expected Save

Question 6. Project management includes:

a) All answers apply
b) Controlling
c) Directing
d) Planning
e) Organizing Save

Question 7. What part of a "work breakdown structure" is used to describe the work usually done by one of the workgroups?

a) Sub-task
b) Work package
c) None apply
d) Task
e) SOW

Question 8. Critical path scheduling requires:

a) Well-defined jobs
b) R&D type projects
c) Variable job or task order
d) Dependent jobs or tasks
e) Jobs that can be conducted concurrently

Note: It is recommended that you save your response as you complete each question.

Question 9. In using modern project management, what does the "rule of urgency" NOT create?

a) Teamwork
b) Team motivation
c) Team disillusionment
d) Performance
e) Action

Question 10. What is the term used to describe the longest path time through a CPM network?

a) Constrained path
b Slacktime path
c) No answers apply
d) Work time path
e) Critical path

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M91827469

Have any Question?


Related Questions in Operation Management

Conflictdefine functional versus dysfunctional conflict in

Conflict Define functional versus dysfunctional conflict in a work group and explain how you can increase functional conflict and decrease dysfunctional conflict. Develop a response that includes examples and evidence to ...

For this assignment you will need to find 2 articles in

For this assignment, you will need to find 2 articles in business that can help describe what are IT strategic initiative being undertaken by an organization are like. Choose a different organization for each of the arti ...

Coping with problems joe is a little nervous he has just

Coping With Problems Joe is a little nervous. He has just been transferred from another plant to take over a production line. Production is down and there is a serious problem with absenteeism. To make matters worse, the ...

Over 30 years ago michael porter identified a holistic

Over 30 years ago Michael Porter identified a holistic approach to understanding how competitive forces shape strategy. He posited that the only way to truly insulate an organization from underlying economic volatility i ...

You are the contracting officer for an air-to-ground

You are the contracting officer for an air-to-ground missile development program. A contract for pre-production models of the missile was awarded by your predecessor and the contractor is behind schedule. In a program me ...

The ikea case provides an excellent opportunity to apply

The IKEA case provides an excellent opportunity to apply strategic management concepts to a large privately-held company that is expanding into India. IKEA is a Netherlands-based Swedish company with a presence in 44 cou ...

Can you answer for me the following questions about social

Can you answer for me the following questions about social loafing and the three main causes of free-riding. 1. Give a description of the phenomenon of social loafing. 2. Give a description of the phenomenon of free-ridi ...

1 analyzing the bridgestonefirestone and ford motor company

1. Analyzing the Bridgestone/Firestone and Ford motor company, is it sufficient to use the ISO/QS 9000 standards as the main basis of vendor/product selection? 2. What position to these cars company ( 1. Volkswagen, 2. F ...

Research the effect of primary and secondary seat belt laws

Research the effect of primary and secondary seat belt laws on the occurrence of motor-vehicle injuries and fatalities. Explain how epidemiologic studies influenced the development of current seat belt laws. Describe how ...

Please provide a brief paragrap of the key takaways from

Please provide a brief paragrap of the key takaways from each of the following topics: Designing Clear Visuals in business reports Designing Successful Documents and Websites Writing Winning Proposals

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As