Question 1. 1.

A/an _________ activity has more than one dependency arrow flowing from it.

Parallel

Critical path

Burst

Merge

Independent

Question 2. 2.

Which of the following is least likely to be included in a Work Package?

Materials

Labor

Overhead

Duration

Responsibilities

Question 3. 3.

The requirement for a freshly poured foundation to cure before beginning construction is an example of which of the following type of lag?

Start to Start

Start to Finish

Finish to Finish

Finish to Start

Any of these could be correct

Question 4. 4.

The first step of project scope definition is to

Analyze the strategic plan

Analyze the current budget plan

Meet with team members

Select team members

Define the overall objective to meet the customer's needs

Question 5. 5.

People working on prototype development needing time to interact with the design engineers after the design is completed is an example of:

Hidden interaction costs

Things going wrong on a project

Normal conditions not applying

Changes in project scope

None of these are correct

Question 6. 6.

General and Administrative costs are usually allocated as a percent of the total of a direct cost such as labor, materials, or equipment.

True

False

Question 7. 7.

If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first?

Check to see which activities cost the least

Check to see which activities have the longest duration

Check to see which activities are on the critical path

Check to see which activities have the most slack

Check to see which activities have the highest risk

Question 8. 8.

Scott has just been given a project that has a specific target date. After discussion with top management he finds that while the date is important the cost is more important and a slip in delivery would be acceptable if required to meet the cost targets. The target date is best classified as

Constrain

Enhance

Accept

Limit

Optional

Question 9. 9.

The backward pass in project network calculations determines the

Latest time's activities can begin

Earliest time's activities can be finished

Critical path

Both A and C are correct

A, B, and C are all correct

Question 10. 10.

By definition, the critical path always has zero slack.

True

False

Business Management, Management Studies

  • Category:- Business Management
  • Reference No.:- M91726484
  • Price:- $20

Priced at Now at $20, Verified Solution

Have any Question?


Related Questions in Business Management

Name a company that addressed a recent ethical problem in a

Name a company that addressed a recent ethical problem in a positive way. Also, explain how or if this positively affects us as a community?

When it is appropriate to use the trade-off process what

When it is appropriate to use the trade-off process. What conditions apply, and the technical evaluation criteria that might be used?

Need help with a essay with the following phrase for

Need help with a essay with the following phrase for analyzing : " Capitalism is at the heart of how people and organisations are managed in contemporary society" May i ask for a better explanation of the question? Also ...

How could these three tenets of the auburn creed be used to

How could these three tenets of the Auburn Creed be used to motivate others: "I believe that this is a practical word and that I can count only on what I earn. Therefore, I believe in work, hard work." "I believe in educ ...

How can these two tenets of the auburn creed by used in

How can these two tenets of the Auburn Creed by used in addressing teamwork issues: "I believe in honesty and truthfulness, without which I cannot win the respect and confidence of my fellow men." "I believe in the human ...

Discuss the advantages of having and interacting in a

Discuss the advantages of having and interacting in a diverse workplace. Consider the wide range of ideas and perspectives that a range of team members bring to a team, that are of differing ages, ethnic backgrounds and ...

Parmigiano-reggiano global recognition of geographical

Parmigiano-Reggiano: Global Recognition of Geographical Indications What historical factors have helped support the consortium's claims for the geographic specificity of Parmigiano-Reggiano and Parmesan? What are the eco ...

Communication planthis communication plan will be a roadmap

Communication Plan This communication plan will be a roadmap on how the new division will best be able to communicate with Biotech's corporate headquarters, suppliers, other divisions, and internally. This should lay out ...

Discuss strategies to obtain feedback from a customer and

Discuss strategies to obtain feedback from a customer and clients when working in sales.

Describe different networking methods and the advantages

Describe different networking methods and the advantages and disadvantages of them?

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As