The Project Management Office for your company would like to see the critical path for your major milestones, as well as the earliest-latest starting and finishing times. Based on the project plan developed earlier in the project, the milestones, dependencies, and effort times are as follows:

Milestone

Predecessor

Efforts (Weeks)

A


4

B


6

C

A, B

7

D

B

8

E

B

5

F

C

5

G

D

7

H

D, E

8

I

F, G, H

4

Using Excel QM software (located in the Add-ins section or across the tool bar) and looking in the Project Management category (located in either the QM or Render links in Excel QM), select the Predecessor List (AON) link.

Fill in the data per the table above. Generate the critical path graph (by checking "Include the graph") when generating the appropriate matrix. This selection will also generate the earliest-latest starting and finishing times.

Copy the input table, resulting table, and critical path Gantt chart in to your team's Risk Management Plan under section 2.4.2 Quantitative Analysis - Excel QM.

Part B

The Project Management Office has received a decision from the senior leadership of your organization, to bring the project timeline in from the current 26 weeks (based on the information above). Your team has been asked to look at crashing the schedule to 14 weeks.

The Project Management Office would like to know if the schedule can be crashed to 14 weeks and what the cost would be to crash the schedule.

Using Excel QM software and looking in the Project Management category, choose the Crashing link. Fill in the data based on the 9 milestones from both tables (Part A and B). Copy the resulting table in to your team's Risk Management Plan in section 2.4.2 Quantitative Analysis - Excel QM after the results of Part A.

Note: you may need to add the Solver tool to Excel QM if you do not see it in the Data Analysis section of QM. To do this go to the main TOOLS menu in the top tool bar, click on Add-Ins, and then select Solver.

In addition to the information in Part A you have the following data:

Milestone

Crash Time (Weeks)

Normal Cost

Crash cost per week

A

1

$8,000

$1,500

B

2

$12,000

$1,500

C

3

$14,000

$2,000

D

4

$19,000

$3,000

E

2

$13,000

$1,000

F

3

$9,000

$500

G

2

$16,500

$2,000

H

4

$22,000

$3,000

I

2

$5,500

$500

Please note that the crash cost is a per week cost and the tool asks for total cost (normal and crash).

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M92769919

Have any Question?


Related Questions in Operation Management

1 artificial intelligencea define this digital marketing

1. Artificial Intelligence a) Define this digital marketing tactic today. b) Share (what is) the innovation relating to this tactic. c) How this could be used for marketing in the future? 2. Video Marketing a) Define thi ...

1 the priorities of organizations are important and

1. The priorities of organizations are important, and organizational theory defines the methods that organizations should use to determine and define their priorities and communicate them to stakeholders. Please briefly ...

1- consequences of dysfunctional stress include each of the

1- Consequences of dysfunctional stress include each of the following except: A. it makes us fatter. B. it weakens our immune system. C. it can cause headaches, depression and illness. D. it can cause us to perform at a ...

1 one of the most difficult skills to master for new

1. One of the most difficult skills to master for new supervisors is effective delegation. Discuss a time when a supervisor or other person in authority delegated a responsibility to you. How did you feel about receiving ...

Assignmenttechnology can be a vital component of training

Assignment Technology can be a vital component of training delivery. Use online library resources to read about training technology. Using your own experience, module readings, Internet research, and references from the ...

You are ceo of a major us humanitarian organization your

You are CEO of a major U.S. humanitarian organization. Your team primarily sends financial AID to the schools in developing countries to provide better education for children. Your organization considers sending substant ...

1 why does beachhead acquisition takeover this form of

1. Why does beachhead acquisition takeover this form of takeover exist? What would a person highly value if he/she thinks that beachhead takeovers are a good idea? 2. Explain briefly your understanding for below; 1.WHS R ...

1 discuss the 2 main pricing strategies for a new product2

1. Discuss the 2 main pricing strategies for a new product. 2. Describe a situation in which you are part of a formal work group (while working in a job or as a student) and one of the members of the group does not contr ...

Marketing classtall timber lumber supplyjoe hanratty owner

Marketing class Tall Timber Lumber Supply Joe Hanratty, owner of Tall Timber Lumber Supply, feels his business is threatened by a tough new competitor. And now Joe must decide quickly about an offer that may save his bus ...

1 what are the of individualism versus collectivism and

1. What are the of Individualism versus collectivism and Masculinity versus Femininity of Samsung & Huawei ? 2. What is the best equilibrium model while working in a group setting for a team project. 3. Discuss the advan ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As