Ask Operation Management Expert

Q1: In a single sampling plan the sample size n =5. The submitted lot has on an average 25% defective items. Three acceptance numbers ( c = 0, c =1, and c=2) are being negotiated between the manufacturer and the buyer. Which acceptance number is most desirable from the manufacturer's viewpoint. You may use the following OC curve to find the answer.

a)  c = 0

b)  c = 1

c)   c = 2

926_Find the project duration.png

Q 2: In a double sampling plan the two acceptance numbers are: c1 = 8 and c2 = 12. The number of defectives found in the first sample is 9. Therefore, a second sample is taken. What is the maximum number of defectives allowed in the second sample for the lot to be accepted?

a) 0

b) 1

c) 2

d) 3

e) 4

Twenty samples of n = 200 were taken by an operator at a workstation in a production process. The number of defective items in each sample was recorded as follows. Answer

Q 3.

  Number                    Number

Sample  of Defectives      Sample    of Defectives

  1       12               11         16

  2       18               12         15

  3       10               13         13

  4       15               14         16

  5       16               15         18

  6       19               16         17

  7       17               17         18

  8       12               18         20

  9       11               19         21

  10      14               20         22

Management wants to develop a p-chart. The desired confidence level is 80.0 percent.

Q 3: What is the upper control limit?

Cans of soup are supposed to weigh exactly 16 oz. Inspectors want to develop process control charts. They take eight samples of five boxes and weigh them. They obtain the following data. Answer Q 4, and Q 5.

Sample      Mean       Range

1       15.2         1.8

2       14.6         0.7

3       16.5         0.5

4       18.1         0.4

5       13.2         0.2

6       16.0         0.4

7       15.9         0.5

8       14.8         0.9

 

Q 4: What is the upper control limit for the x-bar chart?

Q 5: What is the upper control limit for the R chart?

Cholesterol Palace is a fast-food restaurant. Management was concerned with errors in filling orders at its drive-up window. It hired several undercover quality inspectors to randomly place 100 orders while the process seemed to be in control. The completed orders were then checked for accuracy. The following table shows the results of the survey. Answer Q 6, Q 7, and Q 8.

Defect                                                Frequency

Incomplete, shorted order                              12

Unordered items dispensed                             2

Wrong product dispensed                               14

Wrong toppings                                            14

Wrong size drink                                            2

Drink lid not sealed                                        17

No drinking straw with soft drink order              0

No napkins                                                  18

Far too many condiment packets                     65

No salt with sandwich or fries order                  10

Wrong change                                               3

Other                                                          12

QC 6: Use these data to estimate the average number of defects per order.

QC 7: What is the lower control limit for a c-chart. Use z =3.

QC 8: A quality inspector just used the drive-up window and now checks her order. Her cheeseburger has mustard on it although she ordered it without ketchup or mustard. Three handfuls of ketchup and mustard packets are in the sack, but no napkins. And hot coffee has spilled because the lid wasn't properly sealed. Is the drive-up process in control?

 PROBLEMS ON PROJECT MANAGEMENT

Q 9: Use the data given in the following table and the relationships between activities shown in the Activity on Node (AON) network. Find the project duration (earliest completion time of the project).

 

1670_Find the project duration1.png

Activity

A

B

C

D

E

F

G

Time (days)

5

6

9

4

9

3

4

a)  21

b)  22

c)   25

d)  28

e)  31

Q 10: Use the data given in the following table and the relationships between activities shown in the Activity on Node (AON) network. What is the latest start time of activity C if the project completion time (due date) is set at 33 day?

58_Find the project duration2.png

Activity

A

B

C

D

E

F

G

Time (days)

5

6

9

4

9

3

4

a)  5

b)  7

c)   33

d)  Zero (0)

You may use the following table.

Activity

Immediate Predecessor

Time

Late Start

Late Finish

A

 

 

 

 

B

 

 

 

 

C

 

 

 

 

D

 

 

 

 

E

 

 

 

 

F

 

 

 

 

G

 

 

 

33

Q 11: The data for a Time-Cost CPM Scheduling model analysis are given below. The times are in days. What is the minimum cost to complete this project in 14 days?

Activity

Immediate Predecessor

Normal Time

Crash Time

Normal Cost ($)

Crash Cost ($)

A

None

4

2

2000

4000

B

A

4

3

3000

6000

C

A

2

1

2000

2500

D

B and C

4

2

5000

5600

E

D

3

1

6000

9000

a)  18,000

b)  27,100

c)   18,300

d)  300

Q 12: You have collected the data for a Time-Cost CPM Scheduling model analysis. The time is in days and the project "direct costs" are given below.

Activity

Immediate Predecessor

Normal Time (days)

Crash Time (days)

Normal Cost (Direct) $

Crash Cost (Direct) $

A

None

3

2

300

400

B

A

3

3

100

100

C

A

1

1

200

200

D

B and C

3

2

400

550

E

D

2

1

500

900

F

E

3

3

200

200

G

F

2

2

100

100

The network for this project is given below.

641_Find the project duration3.png

The indirect costs for the project are determined on a daily duration basis and are given below:

Total indirect costs for 16 days of project duration: $ 600

Total indirect costs for 15 days of project duration: $ 400

Total indirect costs for 14 days of project duration: $ 200

Total indirect costs for 13 days of project duration: $ 100

At what project duration do we achieve the lowest total project cost (i.e., direct plus indirect costs)?

(a) 16 days

(b) 15 days

(c) 14 days

(d) 13 days

Consider a project having the following ten activities. Answer Q13 and Q14.

Activity

A

B

C

D

E

F

G

H

I

J

Immediate Predecessors

None

None

A

A,B

C,D

D

C

E,G

E,F

H,I

Time (weeks)

 

7

3

5

6

4

4

9

8

6

5













Q13: What is the critical path?

a) A-C-G-H-J

b) A-B-C-D-E-F-G-H-I-J

c) A-D-E-H-J

d) B-D-F-I-J

Q 14: What is the slack time of activity B?

a)  zero

b)  8

c)   11

d)  3

e)  19

You may use the following table.

Activity

Immediate Predecessor

Time

Early Start

Early Finish

Late Start

Late Finish

Slack Time

A

 

 

 

 

 

 

 

B

 

 

 

 

 

 

 

C

 

 

 

 

 

 

 

D

 

 

 

 

 

 

 

E

 

 

 

 

 

 

 

F

 

 

 

 

 

 

 

G

 

 

 

 

 

 

 

H

 

 

 

 

 

 

 

I

 

 

 

 

 

 

 

J

 

 

 

 

 

 

 

Problems on Scheduling

Q 15: A single machine work center has five jobs assigned to it. They are labeled, in the order of their arrival in the shop, as jobs A, B, C, D and E. The work center may work on only one job at a time and must complete any job it starts before starting another job. Job A has a processing time of 6 days and is due to the customer in 9 days. Job B has a processing time of 2 days and is due in 16 days. Job C has a processing time of 4 days and is due in 10 days. Job D has a processing time of 3 days and is due in 7 days. Job E has a processing time of 5 days and is due in 12 days. Using the first-come-first-served priority rule, what is the number of late (tardy) jobs?

Job

Time

Due Date

Completion Time

Tardiness

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Q 16: A single machine work center has five jobs assigned to it. They are labeled, in the order of their arrival in the shop, as jobs A, B, C, D and E. The work center may work on only one job at a time and must complete any job it starts before starting another job. Job A has a processing time of 6 days and is due to the customer in 9 days. Job B has a processing time of 2 days and is due in 16 days. Job C has a processing time of 4 days and is due in 10 days. Job D has a processing time of 3 days and is due in 7 days. Job E has a processing time of 5 days and is due in 12 days. Using the shortest (earliest) due date rule, what is the average completion (flow) time of all jobs?

Job

Time

Due Date

Completion Time

Tardiness

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Q 17: A single machine work center has five jobs assigned to it. They are labeled, in the order of their arrival in the shop, as jobs A, B, C, D and E. The work center may work on only one job at a time and must complete any job it starts before starting another job. Job A has a processing time of 6 days and is due to the customer in 9 days. Job B has a processing time of 2 days and is due in 16 days. Job C has a processing time of 4 days and is due in 10 days. Job D has a processing time of 3 days and is due in 7 days. Job E has a processing time of 5 days and is due in 12 days. Using the shortest processing (operating)) time priority rule, what will be the average tardiness of these orders?

Job

Time

Due Date

Completion Time

Tardiness

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Q 18:   A single machine work center has five jobs assigned to it. They are labeled, in the order of their arrival in the shop, as jobs A, B, C, D and E. The work center may work on only one job at a time and must complete any job it starts before starting another job. Job A has a processing time of 6 days and is due to the customer in 9 days. Job B has a processing time of 2 days and is due in 16 days. Job C has a processing time of 4 days and is due in 10 days. Job D has a processing time of 3 days and is due in 7 days. Job E has a processing time of 5 days and is due in 12 days. Using the shortest processing (operating)) time priority rule, what will be the average number of jobs in the system?

Job

Time

Due Date

Completion Time

Tardiness

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Q 19: A machine shop has two machines, M1 and M2. Four jobs A, B, C, and D need to be processed through machines M1 first and M2 second. Job A will take one hour on machine M1 and three hours on machine M2. Job B will take three hours on M1 and two hours on M2. Job C, takes seven hours on M1and three hours on M2. Job D, requires five hours on M1 and one hour on M2. Using Johnson's rule, in what order should these jobs be done?

Q 20: Consider the following data for a five-job, 2-machine, flow-shop problem. Find the value of make-span (minimum time to complete all jobs) using the sequence ABCDE. 

 

Time

Job

M1

M2

A

1

2

B

4

2

C

1

3

D

5

4

E

3

5

You may use the following Gantt Chart template.

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M9808088

Have any Question?


Related Questions in Operation Management

Conflictdefine functional versus dysfunctional conflict in

Conflict Define functional versus dysfunctional conflict in a work group and explain how you can increase functional conflict and decrease dysfunctional conflict. Develop a response that includes examples and evidence to ...

For this assignment you will need to find 2 articles in

For this assignment, you will need to find 2 articles in business that can help describe what are IT strategic initiative being undertaken by an organization are like. Choose a different organization for each of the arti ...

Coping with problems joe is a little nervous he has just

Coping With Problems Joe is a little nervous. He has just been transferred from another plant to take over a production line. Production is down and there is a serious problem with absenteeism. To make matters worse, the ...

Over 30 years ago michael porter identified a holistic

Over 30 years ago Michael Porter identified a holistic approach to understanding how competitive forces shape strategy. He posited that the only way to truly insulate an organization from underlying economic volatility i ...

You are the contracting officer for an air-to-ground

You are the contracting officer for an air-to-ground missile development program. A contract for pre-production models of the missile was awarded by your predecessor and the contractor is behind schedule. In a program me ...

The ikea case provides an excellent opportunity to apply

The IKEA case provides an excellent opportunity to apply strategic management concepts to a large privately-held company that is expanding into India. IKEA is a Netherlands-based Swedish company with a presence in 44 cou ...

Can you answer for me the following questions about social

Can you answer for me the following questions about social loafing and the three main causes of free-riding. 1. Give a description of the phenomenon of social loafing. 2. Give a description of the phenomenon of free-ridi ...

1 analyzing the bridgestonefirestone and ford motor company

1. Analyzing the Bridgestone/Firestone and Ford motor company, is it sufficient to use the ISO/QS 9000 standards as the main basis of vendor/product selection? 2. What position to these cars company ( 1. Volkswagen, 2. F ...

Research the effect of primary and secondary seat belt laws

Research the effect of primary and secondary seat belt laws on the occurrence of motor-vehicle injuries and fatalities. Explain how epidemiologic studies influenced the development of current seat belt laws. Describe how ...

Please provide a brief paragrap of the key takaways from

Please provide a brief paragrap of the key takaways from each of the following topics: Designing Clear Visuals in business reports Designing Successful Documents and Websites Writing Winning Proposals

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As