Develop an in-depth schedule for your initial project based on the Work Breakdown Structure you have completed in Unit III. Please refer to the "INTEGRATED PROJECT: Developing the Project Schedule" Be sure to include-

1. An activity precedence diagram

2. An activity duration table

3. A network diagram and Gannt charts

Exercise 1

Suppose we have a complete activity predecessor table (shown below) and we wish to create a network diagram highlighting the activity sequence for this project. Using MS Project, enter the activities, their durations, and their predecessors for activities A through E. Note that all duration times are in days.

Project: Remodeling an Appliance

Activity

 

Duration

Predecessors

A

Conduct competitive analysis

3

 

B

Review field sales reports

2

 

C

Conduct tech capabilities assessment

5

 

D

Develop focus group data

2

A, B, C

E

Conduct telephone surveys

3

D

F

Identify relevant specification improvements

3

E

G

Interface with marketing staff

1

F

li

Develop engineering specifications

5

G

I

Check and debug designs

4

Ii

1

Develop testing protocol

3

G

K

Identify critical performance levels

2

1

L

Assess and modify product components

6

I, K

M

Conduct capabilities assessment

12

L

N

Identify selection criteria

3

M

0

Develop RFQ

4

M

P

Develop production master schedule

S

N, 0

Q

Liaise with sales staff

1

P

R

Prepare product launch

3

Q

Exercise 2

Now, continue developing your Gantt chart with the rest of the information contained in the table above and create a complete activity network diagram for this project.

Exercise 3

Identify the critical path for the project shown in Exercise 1. How can you tell? Hint Click on the "Tracking Gantt" option.

Exercise 4

Suppose that we wished to incorporate lag relationships into a Remodeling an Appliance activity network. Consider the table shown below and the lag relationships noted. Develop an MS Project Gantt chart that demonstrates these lags.

Activity                          Duration               Lag Relationship

A Wiring                             6                             None

B Plumbing                          2                             None

C HVAC                              3            Wiring (Finish to Start), Plumbing (Finish to Finish)

D Interior  Construction         6                     HVAC (Start to Start)

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M91269222
  • Price:- $155

Guranteed 48 Hours Delivery, In Price:- $155

Have any Question?


Related Questions in Operation Management

The article as a synopsis is about crisis management though

The article as a synopsis is about crisis management. Though to go a bit further, it is also not only about managing a crisis, but attempting to plan as well as possible to avoid crisis. You cannot plan for everything, s ...

Assignment presentationpeer reviewtwo of your fellow

Assignment: Presentation/Peer Review Two of your fellow classmates are thinking about joining your practice. They are somewhat anxious because they do not know much about your practice. You want to impress upon them the ...

Southwest airline a proposal has been made to offer a

Southwest airline: A proposal has been made to offer a business class on its longer flights. This class would have more comfortable seats, more legroom, and complimentary magazines, movies, meals, drinks, and Wi-Fi. A to ...

1 is price always a result of costs and demand what

1. Is price always a result of costs and demand? What opportunities do businesses have to charge a premium? Give examples. 2. List 5 internal factors for Delta Airlines. Make sure that you discuss the importance of each ...

A decision tree analysis of a problem eliminates the risks

A decision tree analysis of a problem eliminates the risks in decision making. 2) optimistic (risk prone) and pessimistic ( risk adverse) never make the same decision 3) A posterior probability is the probability of a st ...

Business - organizational leadershipthe topic is going to

Business - Organizational Leadership The topic is going to do the research about "Performance Management" This is a presentation assignment and I have to achieve the below points: 1. Learning Outcomes Identify what learn ...

You manage inventory for a ldquosuper centerrdquo take-out

You manage inventory for a “Super Center” take-out deli department that is open 7 days a week. Your best seller is the fried chicken prepared in the store. You order every four days – and it takes the vendor three days t ...

1 are the criticisms make about the authors contention that

1) Are the criticisms make about the author's contention that shareholder are now just passive impotent beneficiaries valid as to tangible property? why or why not? Valid as to intangible property? why or why not? 2) Is ...

According to the washington post ldquofacebook ceo mark

According to the Washington Post, “Facebook CEO Mark Zuckerberg expressed contrition for allowing third-party apps to grab the data of its users without their permission.” Do you think by allowing third-party to access t ...

1 ecological dialogue can best be summarized asa what we

1. Ecological dialogue can best be summarized as: A) what we believe about the environment depends on what we see and feel. B) what we see and feel about the environment depends on what we believe. C) Both A and B are co ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As