Project path A-C-E-J has these activity time estimates in days:

Activity                 Optimistic                   Most Likely                Pessimistic

A                            3                                  4                                 5

C                            9                                 12                               14

E                            12                                15                               20

J                             7                                  9                                9

Compute the expected time or duration for each activity, the variance for each activity, and the expected duration and variance for the path.

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M92098651
  • Price:- $10

Priced at Now at $10, Verified Solution

Have any Question?


Related Questions in Operation Management

Question sampling surveys and polls are three of the ways

Question : Sampling, surveys, and polls are three of the ways in which data is gathered. The results are then presented as information. How can you be fooled by data? Why/How does the data collected in polls and studies ...

When looking at the life of a project plan it is useful to

When looking at the life of a project plan, it is useful to graph and outline the cost variance (CV), and schedule variance (SV). Determining progress, or lack of progress, provides essential information to assess a give ...

Discuss database impact on the workplacediscuss database

Discuss Database impact on the workplace, Discuss database benefits when businesses use queries, Forms, and reports. Discuss at least two security concerns should be discussed with a proposed solution to mitigate the sec ...

1 the bullwhip effect can be measured by comparing the

1. The bullwhip effect can be measured by comparing the variance of orders to the variance of demand at different stages in a supply chain. Which of the following phenomena is typical for measures of the bullwhip effect? ...

Johnson corporation has the following information about a

Johnson Corporation has the following information about a product that it carries in stock: Use Table 7-2. Average demand = 49 units per day Average lead time = 15 days Item unit cost = $62 for orders of less than 400 un ...

1 the us department of commerce has relaxed restrictions on

1. The U.S. Department of Commerce has relaxed restrictions on the export of encryption (Scrambling) software for communications, but it still bans the export of many such applications. Do you agree with such bans? Why o ...

Respond to these question in essay formatoveruse of

RESPOND TO THESE QUESTION IN ESSAY FORMAT..Overuse of ambiguous terms such as it, this, and they should not be used. A. Base on the examples provided in the 1st & 2nd category BELOW, in 175-200 words elaborate/provide a ...

Question when you think of a global organization what

Question : When you think of a global organization, what company would you consider? What has made this company successful on a global level? Please provide a link to the company's website and list at least 3 countries w ...

1 what is the danger of attempting to manage risks without

1. What is the danger of attempting to manage risks without properly researching them? (30–40 words) 2. Explain legal business contracts by your own understanding. 3. Under what circumstances might it be appropriate to a ...

Mick is a project manager at zarlink a multinational

Mick is a project manager at Zarlink, a multinational manufacturer of semiconductors for a variety of high-technology military, medical and consumer applications. Mick is also a part-time MBA student at his local univers ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As