This is an example of a construction project. The construction for a large corporate building must be started by February 19th and completed by the end of the year. The legal contract for the project includes a penalty of $10,000 for every week of delay beyond December 31st. This implies 315 days or 45 weeks for the expected project duration assuming a seven-day work schedule and no holidays in between!

The details of the project activities are as follows –

The project begins with clearing the site, an activity that takes eight weeks. Once the site is cleared, laying of the subsurface drainage takes another eight weeks, followed by filling of the earth which takes 14 weeks. Only after this activity is completed can installation of the artificial turf outside of the building can start – the task then takes 12 weeks. Simultaneously, the work on the building can also start once the site is cleared.

The work on the building starts first by excavating and then by pouring of the concrete basement. Each of these activities takes 4 weeks to complete. Next comes the construction of the walls (12 weeks), followed by constructing the roof (13 weeks). The interiors are then completed (5 weeks) followed by internal painting (4 weeks). However, painting cannot be started until electrical work is completed (4 weeks). The electrical work cannot be started until the outside power lines are laid (8 weeks), which needs an additional activity of getting the permits before it can be started. The permit takes 4 weeks. Assume that you would start on the permits after the excavation activity for the building begins.

Once the roof of the building is erected, work can start simultaneously on the outside lighting (5 weeks), and on the signage and other external landscaping (4 weeks). For simplicity, assume you start the project on February 19th and you follow a 7-day work schedule where each week of an activity’s duration takes 7 days.

Analyze the following questions based on the estimates of the above activities -

1) When do you complete the project?

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M93121068

Have any Question?


Related Questions in Operation Management

Custom copies inc prepares and sells coursepacks which

Custom Copies, Inc., prepares and sells coursepacks, which contain compilations of readings for college courses. A teacher selects the readings and delivers a syllabus to the copy shop, which obtains the materials from a ...

1 what are the differences between a project operations and

1. What are the differences between a project, operations, and a program? Please be sure to provide an example and justification for each. Your response should be at least 200 words in length. 2. What is advertising wear ...

1 create a professional memo to the hospital ceo in your

1. Create a professional memo to the hospital CEO. In your memo, explain current trends and future challenges of health information exchanges. Include benefits and challenges to joining a HIE. Your memo should include at ...

1 is pursuing this campaign a smart investment for droga 5

1. Is pursuing this campaign a smart investment for Droga 5 - and for the proposed partners Random House, Roc Nation, and Microsoft? 2. What would you advise as a solution to the conflict between Microsoft and Roc Nation ...

As an assistant director for the public health alliance of

As an Assistant Director for the Public Health Alliance of a major metropolitan area made up of a number of public health organizations in the area. You have been tasked with the responsibility to develop a report, which ...

In the textbook reading you learned about the importance of

In the textbook reading, you learned about the importance of audience analysis when making a presentation. In the Topic Material, "Selling Yourself and Your Ideas to Senior Management," there are tips about making effect ...

Format to followintroductiondefinitionsshow

Format to follow Introduction definitions, show understanding give examples to illustrate your answer - MENA region /business/ is higher level explain conclude cite sources if quoted - but not essential approx 250 words ...

For this assignment you will create a harvest plan by

For this assignment, you will create a harvest plan by describing in detail which exit strategies you will use, how you will execute the plan, and all the intricate parts of your plan. Follow the steps below to complete ...

1- at the beginning of the quarter sara sat down with her

1- At the beginning of the quarter, Sara sat down with her manager and set three goals. If Sara achieves those three goals in the next three months, she will receive a $1,000 bonus. Which advantage of individual incentiv ...

Questiona company produces to a seasonal demand with the

Question: A company produces to a seasonal demand, with the forecast for the next 12 months as given below. Month Demand January 600 February 700 March 800 April 700 May 600 June 500 July 600 August 700 September 800 Oct ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As