Project Management Analytics Exercise

This is an example of a construction project. The construction for a large corporate building must be started by February 19th and completed by the end of the year. The legal contract for the project includes a penalty of $10,000 for every week of delay beyond December 31st. This implies 315 days or 45 weeks for the expected project duration assuming a seven-day work schedule and no holidays in between!

The details of the project activities are as follows –

The project begins with clearing the site, an activity that takes eight weeks. Once the site is cleared, laying of the subsurface drainage takes another eight weeks, followed by filling of the earth which takes 14 weeks. Only after this activity is completed can installation of the artificial turf outside of the building can start – the task then takes 12 weeks. Simultaneously, the work on the building can also start once the site is cleared.

The work on the building starts first by excavating and then by pouring of the concrete basement. Each of these activities takes 4 weeks to complete. Next comes the construction of the walls (12 weeks), followed by constructing the roof (13 weeks). The interiors are then completed (5 weeks) followed by internal painting (4 weeks). However, painting cannot be started until electrical work is completed (4 weeks). The electrical work cannot be started until the outside power lines are laid (8 weeks), which needs an additional activity of getting the permits before it can be started. The permit takes 4 weeks. Assume that you would start on the permits after the excavation activity for the building begins.

Once the roof of the building is erected, work can start simultaneously on the outside lighting (5 weeks), and on the signage and other external landscaping (4 weeks). For simplicity, assume you start the project on February 19th and you follow a 7-day work schedule where each week of an activity’s duration takes 7 days.

Analyze the following questions based on the estimates of the above activities -

You have a few proposals to expedite the completion of the project. Analyze each proposal independently of the other proposals and comment on which proposal (if any) would you adopt for expediting the project?

a) Expedite the wall construction activity – this would cost $20000 and would reduce the activity by six weeks

b) The same as the above proposal but in addition, use a double shift on filling the earth. This would cost $10,000 and would reduce the filling activity by 5 weeks.

c) Construction of the roof is important. You could use additional labor for $9000 and cut six weeks off the original duration of the activity.

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M93121067

Have any Question?


Related Questions in Operation Management

Access to clean water is considered by many to be a basic

Access to clean water is considered by many to be a basic human right, yet significant numbers of people do not have it. Focus on a specific geographical area and identify obstacles and propose solutions. I have decided ...

Managing transportation and distribution in supply chains1-

Managing Transportation and Distribution in Supply Chains 1- Typically, various modes are used to move goods in supply chains. One of such modes is referred to as “Intermodal”. Clearly describe what it entails and explai ...

Strategies for survival and morality consider the methods

"Strategies for Survival and Morality": Consider the methods prisoners of the Russian Gulags survived as identified by Applebaum. Determine which one or more of the methods you believe you would most likely take if you w ...

Answer the following question identify two ways that

Answer the following Question : Identify two ways that healthcare organizations perform marketing related data capture that do not violate any regulatory stipulations. Analyze and discuss how these might change in the fu ...

1 identify 3-4 ethical issues that are raised by the use of

1) Identify 3-4 ethical issues that are raised by the use of smartphones in the workplace. 2) Discuss if your employer (or previous employer) had rules regarding the usage of smartphones in meetings or in the workplace. ...

1 discuss the concept of open space classrooms are open

1. Discuss the concept of open space classrooms. Are open space classrooms the best option for 2018? Why or why not? Use the text and other sources to support your answer.  2. Discuss the importance for public managers t ...

It is april 1 2018 and indra nooyi chief executive officer

It is April 1, 2018, and Indra Nooyi, Chief Executive Officer of PepsiCo, has hired you as a troubleshooter for the company. Your task is assess PepsiCo’s portfolio of businesses and make recommendations to top managemen ...

From the second e-activity analyze the branches of

From the second e-Activity, analyze the branches of government of your state with respect to the extent that each branch is associated with health care. Determine whether your state government will participate in either ...

Assignment1 construct a symbolic model of the logical

Assignment 1) Construct a symbolic model of the logical structure of the following sentence. Construct a truth table for the symbolic model. 2) Apply PL to construct a symbolic model of the logical structure of each of t ...

A healthcare organization wants to change and restructure

A healthcare organization wants to change and restructure things to figure out their financial issues. 1. What measures can they use along the way to determine the success of the change? 2. What are the benchmarks in the ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As