Ask Operation Management Expert

Project Closure

Project Management Ch 14

 

1:Which of the following is not a wrap-up closure activity that might be found on a checklist?

A)Getting delivery acceptance from the customer

B)Reassigning project team members

C)Closing accounts and seeing all bills are paid

D)Evaluation of team performance

E)Creating a final report

2:The content of the final report typically includes the following topics EXCEPT

A)Lessons learned

B)Review and analysis

C)Recommendations

D)Executive summary

E)Team reviews

3:When the project may be completed early with some parts of the project eliminated this is considered to be ___________ closure.

A)Normal

B)Premature

C)Perpetual

D)Changed Priority

E)Failed Project

4:When a project starts with a high priority but it is cancelled because its rank erodes or crashes during its project life cycle, this is an example of what type of project closure?

A)Normal

B)Premature

C)Perpetual

D)Failed Project

E)Changed Priority

5:Which of the following summarizes project performance and provides useful information for continuous improvement?

A)Customer acceptance

B)The final report

C)Team evaluation

D)360 degree feedback

E)Project summary

6:Which part of the final report examines in detail the underlying causes of problems, issues, and successes relative to the project and includes concise, factual review statements of the project?

A)Executive summary

B)Review and analysis

C)Recommendations

D)Lessons learned

E)Appendix

7:The purpose of project evaluation is to assess how well

A)The project team performed

B)The team members performed

C)The project manager performed

D)The project team and team members performed

E)The project team, team members and the project manager performed

8:Which of the following would NOT be appropriate to assess when evaluating team performance?

A)How well the team performed in terms of time, cost, and specifications

B)Effectiveness of group decisions

C)Individual strengths and weaknesses

D)Customer satisfaction with project deliverables

E)Trust among group members

9:An analysis carried out during and shortly after the project life cycle that attempts to capture positive and negative learning is represented in which of the following?

A)Scenario analysis

B)Variance analyses

C)Lessons learned

D)Performance evaluation

E)Strategic objectives

10:The process for capturing lessons learned continues to evolve, but there are still many barriers to effectively capitalizing on lessons learned that have been identified. The following are examples of these barriers EXCEPT

A)Lack of time

B)Teams get little direction or support after lessons are reported

C)Lessons learned often degenerate into blame sessions

D)Lessons learned are being used across different locations

E)The organizational culture doesn't support the effort that it takes to capitalize on lessons learned

11:The following are distinguishing characteristics of retrospectives methodology EXCEPT

A)Uses an independent facilitator

B)Establishes in-process learning gates during the project life cycle

C)An owner, typically a team member, is assigned

D)Reviews cannot be linked to percent complete

E)A repository is developed that is easy to use

12:A guide who leads the project team through an analysis of project activities that went well, what needs improvement, and development of a follow-up action plan with goals and accountability is a(n)

A)Owner

B)Project sponsor

C)Project manager

D)Facilitator

E)Mediator

13:More and more companies are discarding the traditional superior-subordinate performance feedback process and replacing it with a multi-rater appraisal called

A)Critical incidences review

B)Management by objectives

C)The 360-degree feedback

D)Team evaluation survey

E)Retrospectives

14:Which of the following is NOT a role of the closure facilitator?

A)Create an environment in which stakeholders feel safe to provide input

B)Lead the team in exploring new ways for solving problems

C)Uses several questionnaires as a starting point to conduct the post-project retrospective

D)Get delivery acceptance from the customer

E)Elicit a 360 degree view and input from all stakeholders to create a more complete picture of project issues

15:Each retrospective is assigned a(n) _________, typically a team member who is very interested in and familiar with the retrospective. This individual will serve as the contact point for anyone needing information relating to the retrospective.

A)Owner

B)Project sponsor

C)Project manager

D)Facilitator

E)Mediator

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M92202383
  • Price:- $10

Priced at Now at $10, Verified Solution

Have any Question?


Related Questions in Operation Management

Conflictdefine functional versus dysfunctional conflict in

Conflict Define functional versus dysfunctional conflict in a work group and explain how you can increase functional conflict and decrease dysfunctional conflict. Develop a response that includes examples and evidence to ...

For this assignment you will need to find 2 articles in

For this assignment, you will need to find 2 articles in business that can help describe what are IT strategic initiative being undertaken by an organization are like. Choose a different organization for each of the arti ...

Coping with problems joe is a little nervous he has just

Coping With Problems Joe is a little nervous. He has just been transferred from another plant to take over a production line. Production is down and there is a serious problem with absenteeism. To make matters worse, the ...

Over 30 years ago michael porter identified a holistic

Over 30 years ago Michael Porter identified a holistic approach to understanding how competitive forces shape strategy. He posited that the only way to truly insulate an organization from underlying economic volatility i ...

You are the contracting officer for an air-to-ground

You are the contracting officer for an air-to-ground missile development program. A contract for pre-production models of the missile was awarded by your predecessor and the contractor is behind schedule. In a program me ...

The ikea case provides an excellent opportunity to apply

The IKEA case provides an excellent opportunity to apply strategic management concepts to a large privately-held company that is expanding into India. IKEA is a Netherlands-based Swedish company with a presence in 44 cou ...

Can you answer for me the following questions about social

Can you answer for me the following questions about social loafing and the three main causes of free-riding. 1. Give a description of the phenomenon of social loafing. 2. Give a description of the phenomenon of free-ridi ...

1 analyzing the bridgestonefirestone and ford motor company

1. Analyzing the Bridgestone/Firestone and Ford motor company, is it sufficient to use the ISO/QS 9000 standards as the main basis of vendor/product selection? 2. What position to these cars company ( 1. Volkswagen, 2. F ...

Research the effect of primary and secondary seat belt laws

Research the effect of primary and secondary seat belt laws on the occurrence of motor-vehicle injuries and fatalities. Explain how epidemiologic studies influenced the development of current seat belt laws. Describe how ...

Please provide a brief paragrap of the key takaways from

Please provide a brief paragrap of the key takaways from each of the following topics: Designing Clear Visuals in business reports Designing Successful Documents and Websites Writing Winning Proposals

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As