Problem:

Page Engineering designs and constructs air conditioning and heating systems for hospitals and clinics. Currently, the company's staff is overloaded with design work. There is a major design project due in 8 weeks. The penalty for completing the design late is $14 000 per week, since any delay will cause the facility to open later than anticipated, and cost the client significant revenue. If the company uses its inside engineers to complete the design, it will have to pay them overtime for all work. Page has estimated that it will cost $12 000 per week (wages and overhead), including late weeks, to have company engineers complete the design. Page is also considering having an outside engineering firm do the design. A bid of $92 000 has been received for the completed design. Yet another option for completing the design is to conduct a joint design by having a third engineering company complete all electromechanical components of the design at a cost of $56 000. Page would then complete the rest of the design and control systems at an estimated cost of $30 000.

Page has estimated the following probabilities of completing the project within various time frames when using each of the three options. Those estimates are shown in the following table:

Option                         On Time            Week Late         2Weeks Late     3Weeks Late

Internal Engineers          .4                     .5                     .1                                 -

External Engineers        .2                     .4                     .3                                 .1

Joint Design                 .1                     .3                     .4                                 .2

What is the best decision based on an expected monetary value criterion? You want the lowest EMV because we are dealing with costs in this problem.

Solve the problem and show all work.

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M91149654

Have any Question?


Related Questions in Operation Management

What criteria should be used during the process of

What criteria should be used during the process of selecting amongst strategic alternatives? WHY? What criteria should be taken into account when debating strategic alternatives. You should list possible strategic option ...

Doing business internationally often involves confronting

Doing business internationally often involves confronting ethical issues that do not arise or that have already been solved to our culture’s satisfaction in domestic companies. An example would be manufacturing operation ...

Refer to the five competitive forces porters five forces

Refer to the five competitive forces (Porter's Five Forces) that determine industry profitability. Are some industries more profitable than others? If so, give an example of a profitable industry and a not-profitable ind ...

Answer the following question how is the npv rule related

Answer the following Question : How is the NPV rule related to the goal of maximizing shareholder wealth, and under what conditions would you expect the NPV and IRR rules to return the same accept / reject decision? Iden ...

1 what is the role of governance in knowledge management

1. What is the role of "Governance" in Knowledge Management system for a not for profit, international organization and government agencies ? 2. How can a person us the consumption and creation of knowledge as a PhD-BA s ...

Bob richards the production manager of stella elements in

Bob Richards, the production manager of Stella Elements, in Boca Raton, Florida, is preparing his quarterly report, which is to include a productivity analysis for his department. One of the inputs is production data pre ...

The heart association plans t install a free blood pressure

The Heart Association plans t install a free blood pressure testing booth at the Palouse mall for a week. Previous experience indicates that, on average, 10 persons per hour request a test and the arrivals are Poisson di ...

1 what are the differences between a project operations and

1. What are the differences between a project, operations, and a program? Please be sure to provide an example and justification for each. Your response should be at least 200 words in length. 2. What is advertising wear ...

Auto data produces custom engineering testing equipment the

Auto Data produces custom engineering testing equipment. The following six orders are currently in the design department: Job Time Since Arrival (weeks ago) Process Time (weeks) Due Date (weeks from now) A 5 3 7 B 6 8 14 ...

Virtual product development vpdthe stage gate product

Virtual Product Development (VPD) The Stage Gate Product Development Process was developed during the 1980’s by Dr. Cooper. Many functional societies, highly innovative management consultants and individual company drive ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As