Consider a project having the following ten activities:

Activity

Immediate Predecessors

Normal Time (weeks)

Normal Cost

($)

Crash Duration

(weeks)

Crash Cost

($)

Max. Weeks Reduced

A

none

7

3,000

6

6,000

1

B

A

8

5,000

6

9,000

2

C

A

2

2,000

1

3,000

1

D

A

4

3,000

4

3,000

0

E

B, C

9

4,000

7

6,000

2

F

C, D

6

4,000

4

9,000

2

G

E

2

3,000

2

3,000

0

H

E, F

9

4,000

7

7,000

2

I

G

1

4,000

1

4,000

0

J

H, I

8

2,000

6

7,000

2

Required:

Question 1) Draw a network diagram. What is the expected project completion time?

Question 2) What is the critical path?

Question 3) What is the most economical way and how much will it cost to reduce the completion time of the project by three weeks? By five weeks? Solve the given numerical problem and illustrate step by step calculation.

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M91162605

Have any Question?


Related Questions in Operation Management

Company pepsico1 summarize the various promotional

Company: PepsiCo 1. Summarize the various promotional strategies used by the PepsiCo in implementing an Integrated Marketing Strategy. 2. Identify the risks associated with promotional campaigns and discuss how PepsiCo c ...

Module readings and assignmentcomplete the following

Module Readings and Assignment: Complete the following readings early in the module: Read the online lectures for the Module From the textbook, Capitalism at the Crossroads: Next Generation Business Strategies for a Post ...

Truefalse1 the root causes of the problems associated with

TRUE/FALSE 1) The root causes of the problems associated with the process are identified using a cause-and-effect diagram ________ 2) The first step in many process improvement projects is to create a map of the process ...

Article strategies for learning from failure by amy c

Article : Strategies for Learning from Failure by Amy C. Edmondson Thread Prompt: Strategies for learning from Failure Edmondson writes "First leaders must understand how the blame game gets in the way and work to create ...

A manufacturer is studying a proposal to install an

A manufacturer is studying a proposal to install an automatic device at one of its production operations. The device would perform the operation in exactly 0.5 minutes. At present, there is a (single server) manual opera ...

1 do you think the consumer knkow or care which outles are

1. Do you think the consumer knkow or care which outles are owned by starbucks and which are franchised? 2. Please discuss, compare and contrast: “charismatic leadership”, “transactional leadership” and “transformational ...

Course project ndash cafr of san francisco-2017after

Course Project – CAFR of San Francisco-2017 After serving the city of San Francisco as Mayor for a year and being inspired by the overwhelming participation of your 1st Town Hall meeting addressing 2018 Proposed Budget, ...

Constructing a flowchart scheduling a meeting marion read

Constructing a Flowchart: Scheduling a Meeting Marion read that even the most routine tasks can be flowcharted and that when they are, the diagram may reveal complexity that is both surprising and unnecessary. She though ...

You have been asked by your health care organization to

You have been asked by your health care organization to provide a detailed report on the benefits of implementing a new health information technology system to comply with the current mandates. Develop a report of 10–12 ...

1 recognizing the difference between cooperation and

1. Recognizing the difference between cooperation and collaboration, explain where the team actually collaborated to produce the course project. 2. How did your experience with this Social Contract during virtual teamwor ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As