Problem 1. A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000. For the work performed to date, the budgeted value is $272,000. What are the cost and schedule variances for the project? What are the SPI and CPI?

Problem 2. A project has just completed its 87th item in the project plan. It was scheduled to have spent $168,000 at this point in the plan, but has actually spent only $156,000. The project manager estimates that the value of the work actually finished is nearly $162,000. What are the spending and schedule variances for the project? What are the SPI and CPI?

Problem 3. The following project is at the end of its 6th week. Find the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the ETC and EAC for the project.

Activity

Predecessor

Duration (wks)

Budget ($)

Actual Cost ($)

%Complete

a

-

2

300

400

100

b

-

3

200

180

100

c

A

2

250

300

100

d

A

5

600

400

20

e

b,c

4

400

200

20

Problem 4.  

Using the concepts from Session 11 reading (textbook and reserved readings), respond to following with a thorough explanation. Include any citations for references used to support your answer.

1. What are some reasons that a failing project still might not be terminated?

2. Who would make the best auditors: outside unbiased auditors or inside auditors who are more familiar with the organization, its procedures, and the project?  Why?

3. Under what circumstances would you change your answer to the previous question?

4. Should the results of an evaluation or audit be shared with the project team?

5. What are the major purposes served by an after-the-fact project evaluation?

Problem 5. Solve the following Case:

Stoneworth Paving Company specializes in highway paving jobs for state of Virginia. When the State first awarded Stoneworth the contract, they stipulated a 1% penalty for each week Stoneworth was late on a completion date. Preston Flintrock, the project coordinator for Stoneworth, began to notice that the last two jobs were three weeks late, and the paving job that was due to be completed in the next two weeks was behind schedule. When Preston went in the field to investigate, he found the job to be understaffed, supplier delays, and a high work rejection/repaving needed. As a result, Preston decided to establish a better system of project control and present it to the boss.

Question 1: If you were Preston, what characteristics would you be looking for in a new control system? Explain

Question 2: Will a new control system be adequate for the problem? Explain

Business Management, Management Studies

  • Category:- Business Management
  • Reference No.:- M92057493
  • Price:- $25

Priced at Now at $25, Verified Solution

Have any Question?


Related Questions in Business Management

Question 1 john runs a fresh fruit stand at the beach

Question 1. John runs a fresh fruit stand at the beach. Unfortunately, his cooling capabilities are limited, hence at the end of the week he has to discard any unsold fruits. John ' s best-selling items are oranges. Ever ...

International business questions -q1 to export or not to

International Business Questions - Q1. To export, or not to export that is the question - Why would you be inclined to export? Or, why would you be disinclined to export? 2. Overcoming Challenges - How would you overcome ...

What kind of issues to managers of virtual teams face in a

What kind of issues to managers of virtual teams face in a business environment?

Compare and contrast the five file system options available

Compare and contrast the five file system options available in Windows Server 2012 R2, and discuss when you think it is appropriate to use each one.

Suppose you have used the following production function to

Suppose you have used the following Production Function to estimate the Industry's average and marginal products for its inputs: Q = 150 L 1/4 K 1/3  M 1/5. Where Q stands for output; L is labor; K is capital (machine ho ...

Explain the purpose of each of the five parts in the ryan

Explain the purpose of each of the five Parts in The Ryan White Care Act. Explain other viewpoints or opposing viewpoints of the Act. Describe your stance on if there is a need for the Ryan White Care Act with the Afford ...

What are three examples of different terminology types used

What are three examples of different terminology types used in health care technology and describe the value for enhancing communication. Provide 1-2 references.

Identify a leader that has used power and influence in a

Identify a leader that has used power and influence in a harmful way. Identify an additional leader who has used power and influence in a positive way. For both of these leaders, state your thoughts on their motives for ...

First think about your own upbringing and values when faced

First, think about your own upbringing and values when faced with an ethical decision, whether it is in a business environment or not. How are your beliefs the same as or different than those of your parents or birth com ...

What types processes or procedures support project

What types processes or procedures support project management, continuous improvement and innovative initiatives?

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As