Problem 1: Consider the following project network and activity times (in days):

1327_project network and activity.jpg

Activity

A

B

C

D

E

F

G

Time                                      1

3

2

5

5

6

2

2

The crashing data for this project are as follows:

 

Times  (days)

Cost ($)

Activity

Normal

Crash

Normal

Crash

A

3

2

800

1400

13

2

1

1200

1900

C

5

3

2000

2800

D

5

3

1500

2300

E

6

4

1800

2800

F

2

1

600

1000

G

2

1

500

1000

a. Find the critical path and the expected project completion time.

b What is the total project cost using the normal times?

Problem 2: Refer to Problem 1. Assume that management desires a 12-day project completion time. Formulate a linear programming model that can be used to assist with the crashing decisions.

b. What activities should be crashed?

c. What is the total project cost for the 12-day completion time?

Problem 3: Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities:

 

 

Immediate

Time (weeks)

Cost ($1000s)

Activity

Description

Predecessor

Normal

Crash

Normal

Crash

A

Plan needs

-

10

8

30

70

B

Order equipment

A

8

6

120

150

C

Install equipment

B

10

7

100

160

D

Set up training lab

A

7

6

40

50

E

Conduct training course

D

10

8

50

75

F

Test system

C, E

3

3

60

-

a. Develop a project network.

b. Develop an activity schedule.

c. What are the critical activities, and what is the expected project completion time?

d. Assume that the company wants to complete the project in six months or 26 weeks. What crashing decisions do you recommend to meet the desired completion time at the least possible cost? Work through the network and attempt to make the crashing decisions by inspection.

e. Develop an activity schedule for the crashed project.

f.  What added project cost is required to meet the six-month completion time?

Business Management, Management Studies

  • Category:- Business Management
  • Reference No.:- M91406879
  • Price:- $60

Priced at Now at $60, Verified Solution

Have any Question?


Related Questions in Business Management

Name a company that addressed a recent ethical problem in a

Name a company that addressed a recent ethical problem in a positive way. Also, explain how or if this positively affects us as a community?

When it is appropriate to use the trade-off process what

When it is appropriate to use the trade-off process. What conditions apply, and the technical evaluation criteria that might be used?

Need help with a essay with the following phrase for

Need help with a essay with the following phrase for analyzing : " Capitalism is at the heart of how people and organisations are managed in contemporary society" May i ask for a better explanation of the question? Also ...

How could these three tenets of the auburn creed be used to

How could these three tenets of the Auburn Creed be used to motivate others: "I believe that this is a practical word and that I can count only on what I earn. Therefore, I believe in work, hard work." "I believe in educ ...

How can these two tenets of the auburn creed by used in

How can these two tenets of the Auburn Creed by used in addressing teamwork issues: "I believe in honesty and truthfulness, without which I cannot win the respect and confidence of my fellow men." "I believe in the human ...

Discuss the advantages of having and interacting in a

Discuss the advantages of having and interacting in a diverse workplace. Consider the wide range of ideas and perspectives that a range of team members bring to a team, that are of differing ages, ethnic backgrounds and ...

Parmigiano-reggiano global recognition of geographical

Parmigiano-Reggiano: Global Recognition of Geographical Indications What historical factors have helped support the consortium's claims for the geographic specificity of Parmigiano-Reggiano and Parmesan? What are the eco ...

Communication planthis communication plan will be a roadmap

Communication Plan This communication plan will be a roadmap on how the new division will best be able to communicate with Biotech's corporate headquarters, suppliers, other divisions, and internally. This should lay out ...

Discuss strategies to obtain feedback from a customer and

Discuss strategies to obtain feedback from a customer and clients when working in sales.

Describe different networking methods and the advantages

Describe different networking methods and the advantages and disadvantages of them?

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As