Prepare a master schedule given this information: The forecast for each week of an eight-week schedule is 30 units. The production run size is 40 units.
The MPS rule is to schedule production if the projected on-hand inventory would be negative without it. Then calculate the units that are available to promise.
Customer orders are follows:
WEEK |
Customer Order
|
1 |
32 |
2 |
15 |
3 |
6 |
4 |
0 |
Show ALL work