Prefab, a furniture manufacturer, uses 20,000 square feet of plywood per month. Its trucking company charges Prefab $400 per shipment, independent of the quantity purchased.

(a) The manufacturer offers an all unit quantity discount with a price of $1 per square foot for orders under 20,000 square feet, $0.98 per square foot for orders between 20,000 square feet and 40,000 square feet, and $0.96 per square foot for orders larger than 40,000 square feet. Prefab incurs a holding cost of 20 percent. What is the optimal lot size for Prefab? What is the annual cost of such a policy? What is the cycle inventory of plywood at Prefab? How does it compare with the cycle inventory if the manufacturer does not offer a quantity discount but sells all plywood at $0.96 per square foot?

(b) Now consider the case where the manufacturer now offers a marginal unit quantity discount for the plywood. The first 20,000 square feet of any order are sold at $1 per square foot, the next 20,000 square feet are sold at $0.98 per square foot, and any quantity larger than 40,000 square feet is sold for $0.96 per square foot. What is the optimal lot size for Prefab given this pricing structure? How much cycle inventory of plywood will Prefab carry given the ordering policy?

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M91640593

Have any Question?


Related Questions in Operation Management

This week you will consolidate the written exercises from

This week, you will consolidate the written exercises from Week 1 to Week 5 based on your personal journal entries and prepare a Microsoft PowerPoint presentation of approximately 15-20 slides to present a summary of you ...

Project management integration framework -

Project Management Integration Framework - Assignment Project Charter Identify a project of interest to you. Make sure the project is not too small nor too big. A great example of a project may be purchasing a home, impl ...

Design and draw a high level ldquoas-isrdquo process

DESIGN and DRAW a high level “as-is” process diagram depicting how a trade would be made, under your trading platform structure. The diagram should be for the model you are supporting which is operations manager for offi ...

Customers must be informed of major changes to a business

Customers must be informed of major changes to a business. Jay's Sporting Goods went through the bankruptcy process and was forced to close its stores. Jay’s also had to inform its loyal customers, those who were part of ...

1 what is the preferred step to be taken by the management

1. What is the preferred step to be taken by the management of a hotel prior to the preparation of an operations budget? a) Benchmark the Competition b) Estimate Future Revenues c) Set Financial Objectives d) Estimate Le ...

1 explain the concept of brand personality what are the

1. Explain the concept of brand personality. What are the dimensions of brand personality? Please explain in detail. What is Nike’s brand personality? 2. Compare the State of Maryland to the Israeli or Jordanian health s ...

1 find an obituary or eulogy of a famous person in the usa

1. Find an obituary or eulogy of a famous person in the USA who died in the past 6 months. Analyze the types of claims the document makes about the accomplishments of the deceased. Explain what types of criteria of evalu ...

You have learned about how to identify a country region

You have learned about how to identify a country, region, community, and site for making a location decision for a Global operation. But, what about the ethics of making a location decision? For example, if an American f ...

Discussion - esea title iafter completing this weeks

Discussion - ESEA Title I After completing this week's readings, access the link below and read the article. ESEA Title I, Part A: Underfunded No Matter How You Measure It. As we look at the numbers "ESEA Title I, Part A ...

Discuss what is involved in directing and managing project

Discuss what is involved in directing and managing project execution as part of project integration management, including the importance of producing promised deliverables, implementing solutions to problems, evaluating ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As