Part A: Project Schedule

Create a multi-level work breakdown structure (WBS) and detailed project schedule, using the information from the "Greendale Stadium Case" located at the end of Chapter 6, and incorporating the following constraints.

Note:When you create your MS Project schedule, you will need to update your project per the following constraints:
The project must consist of at least twenty (20) tasks.
Each task must have a start and finish date that matches the duration noted in the assignment.
Each task must be assigned to a resource (e.g., Demolishing Crew; Construction Crew; Landscaping Crew).
Assume that the crew works during normal weekdays (no weekend work) under normal conditions (8 hours per day).
In terms of holidays, you can assume no work will be done the following days: New Year's Day, President's Day, Good Friday, Good Monday, Friday before Memorial Day, Memorial Day, the business day before Independence Day, Independence Day, the Friday before Labor Day, Labor Day, the day before Thanksgiving Day, Thanksgiving Day, Black Friday (day after Thanksgiving), the business day before Christmas, Christmas Day, the business day after Christmas Day, and New Year's Eve.

Part B: Written Response

Respond to the following questions in a one to two (1-2) page paper based on your project schedule.

When will the project be completed?

What is the critical path for the project?

How much slack / float is in your project? What activities have the greatest slack / float?

Identify the top three (3) activities that you believe could impact the project completion date.

What additional activities you would add to this project to make it more complete, from a project management viewpoint?

Format your assignment according to the following formatting requirements:

Typed, double spaced, using Times New Roman font (size 12), with one-inch margins on all sides.

Include a cover page containing the title of the assignment, the student's name, the professor's name, the course title, and the date.

The cover page is not included in the required page length.

Click here to view the grading rubric.

PART 2

Project Schedule

This assignment consists of two (2) parts: a project schedule, and a written response. You must submit both parts as separate files for the completion of this assignment. Label each file name according to the part of the assignment it is written for.

Part A: Project Schedule

In Assignment 2, you developed a project plan. Now, using the information from your project proposal, create a multi-level work breakdown structure (WBS) and detailed project schedule.

Your project must include the following criteria:

The project must consist of at least twenty-five (25) tasks.

Each task must contain a start date, a finish date, and have main staffing and non-staffing resources assigned.

Assume that your work activities are completed during normal weekdays (no weekend work) under normal conditions (8 hours per day).

In terms of holidays, you can assume no work will be done the following days: New Year's Day, President's Day, Good Friday, Good

Monday, Friday before Memorial Day, Memorial Day, the business day before Independence Day, Independence Day, the Friday before Labor Day, Labor Day, the day before Thanksgiving Day, Thanksgiving Day, Black Friday (day after Thanksgiving), the business day before Christmas, Christmas Day, the business day after Christmas Day, and New Year's Eve.

Part B: Written Response

Write a one to two (1-2) page response in which you:

Analyze your project in terms of project completion, critical path, and slack / float. Specifically, be sure to answer the following:

When will the project be completed?

What is the critical path for the project?

How much slack / float is in your project? What activities have the greatest slack / float?

Summarize the recommendations or improvements you would make to your project schedule. Specifically, be sure to answer the following:

Identify the top three (3) activities that you believe could impact the project completion date.

What additional activities would you add to this project to make it more complete, from a project management viewpoint?

Format your assignment according to the following formatting requirements:

Typed, double spaced, using Times New Roman font (size 12), with one-inch margins on all sides.

Include a cover page containing the title of the assignment, the student's name, the professor's name, the course title, and the date.

The cover page is not included in the required page length.

Business Management, Management Studies

  • Category:- Business Management
  • Reference No.:- M91524757
  • Price:- $30

Priced at Now at $30, Verified Solution

Have any Question?


Related Questions in Business Management

How is vision used to confront resistance to change and

How is vision used to confront resistance to change, and move through it? How can a shared vision possibly facilitate collaboration or ultimately the successful implementation of a change initiative?

Nfs allows the file system on one linux computer to be

NFS allows the file system on one Linux computer to be accessed over a network connection by another Linux system. Discuss the security vulnerabilities of NFS in networked Linux systems, and possible mitigation solutions ...

What happens when your mobile application has to perform in

What happens when your mobile application has to perform in less than ideal circumstances?

What are the different types of survey research error and

What are the different types of survey research error and describe an example of each.

According to firestions tire recall case discuss and

According to Firestion's tire recall case, discuss and evaluate the role of leadership when commercial realities conflict with public concerns, ethical dilemmas that ensue for leaders in such situation and how you sugges ...

What are impacts that flexible work schedules can have on a

What are impacts that flexible work schedules can have on a employee's productivity?

A project requires an initial investment of 800 and grants

A project requires an initial investment of $800 and grants cash flows of $100 at the end of year 1, $200 at the end of year 2, $300 at the end of year 3 and $400 at the end of year 4. At a discount rate of 20 percent, i ...

What tenets of the auburn creed would be attractive

What tenets of the Auburn Creed would be attractive characteristics for skills that a company would need in the future and which tenets are not current?

What resources are you most likely to use for research in a

What resources are you most likely to use for research in a workplace? Discuss secondary resources, and primary resources including observation and surveys. What is a credible resource?

Assume that you are the owner and manager of a small

Assume that you are the owner and manager of a small business. Having a strategy for your business. Be sure to include each of the three primary strategic components.

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As