Oversight

Project Management Ch 16

6th Edition

1:The term that can be defined as a set of principles and processes to guide and improve the management of projects is

A)Project administration

B)Fiduciary responsibility

C)Management

D)Project oversight

E)Project regulation

2:The intent of project oversight includes all of the following EXCEPT

A)Meet the needs of the organization through procedures

B)Support the project manager

C)Meet the needs of the organization through continuous improvement

D)Meet the needs of the organization through improving everyday business activities

E)Meet the needs of the organization through accountability

3:Typical activities of project oversight cover which two dimensions?

A)Organization and project

B)Project and customer

C)Customer and industry

D)Industry and organization

E)Organization and customer

4:At the project level, all of the following are examples of oversight activities EXCEPT

A)Review project objectives

B)Track and assist the project to resolve bottlenecks

C)Project selection

D)Review status reports

E)Audit and review lessons learned

5:The centralized management of projects to ensure that the allocation of resources to projects is directed toward projects that contribute the greatest value to organization goals is known as

A)Portfolio Project Management

B)Project Office Management

C)Project Management Optimization

D)Project Priority Matrix Management

E)Resource Allocation Optimization

6:Project office functions typically include which of the following?

A)Create and maintain the internal project management information system

B)Recruit and select project managers

C)Train personnel in project management techniques

D)Develop risk management programs

E)All of these are typically functions of the project office

7:The in-depth review of individual projects at specific phases in the project life cycle is known as

A)Project Assessment Checkpoint Reviews

B)Go/Kill Decision Review Methodology

C)Phase Gate Methodology

D)Stargate Review Methodology

E)Project Implementation Review

8:During which of the following phase gates would the question of "Does this project align with our strategic direction?" be answered?

A)Proposal

B)Screening and selection

C)Implementation plan

D)Progress evaluation

E)Closure

9:During which of the following phase gates would the questions "Are the resources needed identified and available?" and "Are tasks sequenced and is a time-phased budget established?" be answered?

A)Proposal

B)Screening and selection

C)Implementation plan

D)Progress evaluation

E)Closure

10:Which of the following is not one of the growth levels in the Organization Project Management Maturity Model (OPM3TM)?

A)Repeatable (formal application of project management)

B)Defined (institutionalization of project management)

C)Managed (management of project management system)

D)Expanded (expansion of project management system)

E)Optimized (optimization of project management system)

11:The first appearance of standard approaches to managing projects including scope statements and WBS occurs in which of the following Project Management Maturity Model Levels?

A)Ad Hoc Project Management

B)Formal Application of Project Management

C)Institutionalization of Project Management

D)Management of Project Management System

E)Optimization of Project Management System

12:Project audits are performed on all significant projects and lessons learned are recorded and used on subsequent projects in which of the following Project Management Maturity Model Levels?

A)Ad Hoc Project Management

B)Formal Application of Project Management

C)Institutionalization of Project Management

D)Management of Project Management System

E)Optimization of Project Management System

13:Each gate within the phase gate review process should, at a minimum, include the following EXCEPT

A)Required deliverables

B)A plan to proceed

C)Gate criteria

D)Specific outputs

E)A clear yes/no decision on whether to go ahead

14:In which of the following Project Management Maturity Model Levels is the focus is on continuous improvement through incremental advancements of existing practices and by innovations using new technologies and methods?

A)Ad Hoc Project Management

B)Formal Application of Project Management

C)Institutionalization of Project Management

D)Management of Project Management System

E)Optimization of Project Management System

15:The balanced scorecard model differs from selection models by reviewing projects over a longer horizon ___________ after the project is implemented.

A)1-2 years

B)1-5 years

C)5-10 years

D)10-15 years

E)15 years

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M92202360
  • Price:- $10

Priced at Now at $10, Verified Solution

Have any Question?


Related Questions in Operation Management

Conflictdefine functional versus dysfunctional conflict in

Conflict Define functional versus dysfunctional conflict in a work group and explain how you can increase functional conflict and decrease dysfunctional conflict. Develop a response that includes examples and evidence to ...

For this assignment you will need to find 2 articles in

For this assignment, you will need to find 2 articles in business that can help describe what are IT strategic initiative being undertaken by an organization are like. Choose a different organization for each of the arti ...

Coping with problems joe is a little nervous he has just

Coping With Problems Joe is a little nervous. He has just been transferred from another plant to take over a production line. Production is down and there is a serious problem with absenteeism. To make matters worse, the ...

Over 30 years ago michael porter identified a holistic

Over 30 years ago Michael Porter identified a holistic approach to understanding how competitive forces shape strategy. He posited that the only way to truly insulate an organization from underlying economic volatility i ...

You are the contracting officer for an air-to-ground

You are the contracting officer for an air-to-ground missile development program. A contract for pre-production models of the missile was awarded by your predecessor and the contractor is behind schedule. In a program me ...

The ikea case provides an excellent opportunity to apply

The IKEA case provides an excellent opportunity to apply strategic management concepts to a large privately-held company that is expanding into India. IKEA is a Netherlands-based Swedish company with a presence in 44 cou ...

Can you answer for me the following questions about social

Can you answer for me the following questions about social loafing and the three main causes of free-riding. 1. Give a description of the phenomenon of social loafing. 2. Give a description of the phenomenon of free-ridi ...

1 analyzing the bridgestonefirestone and ford motor company

1. Analyzing the Bridgestone/Firestone and Ford motor company, is it sufficient to use the ISO/QS 9000 standards as the main basis of vendor/product selection? 2. What position to these cars company ( 1. Volkswagen, 2. F ...

Research the effect of primary and secondary seat belt laws

Research the effect of primary and secondary seat belt laws on the occurrence of motor-vehicle injuries and fatalities. Explain how epidemiologic studies influenced the development of current seat belt laws. Describe how ...

Please provide a brief paragrap of the key takaways from

Please provide a brief paragrap of the key takaways from each of the following topics: Designing Clear Visuals in business reports Designing Successful Documents and Websites Writing Winning Proposals

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As