Ask Question, Ask an Expert

+61-413 786 465

info@mywordsolution.com

Ask Operation Management Expert

Need help with this project management question:

This project has three completed activities whose durations are indicated by the blue bars in row 2. The budgeted cost of work scheduled for each task is shown on the bar in row 2.

The budgeted cost of work scheduled for each week is shown on row 3. Notice that the amounts in row 3 add up to the amounts shown on the bars.

Rows 4 and 5 indicate the budgeted cost of work performed and actual cost. Notice that the second task started a week late.

1

Week

1

2

3

4

5

6

7

2

Activity

$60K

$40K


$90K

3

BCWS

60,000

25,000

15,000

-

30,000

30,000

30,000

4

BCWP

60,000


25,000

15,000

30,000

30,000

30,000

5

AC

62,000


26,000

15,000

32,000

33,000

30,000

1.What is the planned value (PV) at the end of week three?

2.What is the earned value (EV) at the end of week three

3.What is the actual cost (AC) at the end of week three?

4.What is the cost variance (CV) at the end of week three?

5.What is the schedule variance (SV) at the end of week three?

6.What is the planned value (PV) at the end of week seven?

7.What is the earned value (EV) at the end of week seven?

8.What is the actual cost (AC) at the end of week seven?

9.What is the cost variance (CV) at the end of week seven?

10.What is the schedule variance (SV) at the end of week seven?

11.What is the cost performance index (CPI) at the end of week seven?

12.What is the schedule performance Index at the end of week seven?

13. If the budget at completion (BAC) for this project is $500,000, what is the Estimate to Complete (ETC) at the end of week seven if the cost and schedule variances experienced are typical of the remainder of the activities?

14.Based on your answer to the previous question, what is the estimate at completion (EAC) for this project?

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M92701652

Have any Question?


Related Questions in Operation Management

Many organizations focus their strategy on providing

Many organizations focus their strategy on providing high-quality customer service and consequently place metric concerning customer relationship management on their balanced scorecards. Consider Sam's Pita Pit and the C ...

The annual demand of a manufacturing component used in

The annual demand of a manufacturing component used in company JB Carry & Co Inc. is 21,000 units. The cost of the component is $82, and holding costs (which includes storage, insurance, and cost of capital) are 38% of t ...

The city of bozeman montana requires job candidates to list

The city of Bozeman, Montana, requires job candidates to list their social networking sites, usernames, and passwords on the city employee application. City Attorney Greg Sullivan explained that the city has “positions r ...

1 whatrsquos the definition of implied falsity provide an

1. What’s the definition of Implied Falsity? Provide an example.   2. What is the distinction between honesty, fairness and integrity? Provide a practical example. 3. The capability maturity model has five levels: chaoti ...

Consumercustomer analysis according to this company

Consumer/customer analysis according to this Company Description [Company name] was started by cofounders ( names ) to innovate in medical technologies dedicated to cure cancer. [Company name] is known best for its great ...

1 under what circumstances should an accountant identify

1. Under what circumstances should an accountant identify potential legal issues? 2. When is it appropriate to take an outsider’s view of a company? When is it appropriate to take an insider’s view of a company? 3. When ...

1 give an example of the following types of decisions that

1) Give an example of the following types of decisions that you have had to make (personal or work-related): Low consequence work-oriented High consequence work-oriented 2) Give an example (personal or work-related) for ...

1 lean six sigma and theory of constraints are independent

1. Lean, Six Sigma, and Theory of Constraints are independent applications and do not support each other. 2. Electronic jobs posting can be viewed as a means to ensure that every applicant has a fair chance, based on his ...

You have been offered two different positions identical

You have been offered two different positions, identical with one exception. Job A allows you to telecommute; Job B does not. 1. Should accept the job that telecommutes? If so, would you pursue a part-time or full-time w ...

Workforce planning manages the flow of people into through

Workforce planning manages the flow of people into, through, and out of the organization. The acquisition and deployment of talent has been focused by many organisations as critical aspects of workforce planning. However ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As