Q. MPS calls for 50 units of Product A also 60 of B. re are presently 25 of Product B on hand. Each A requires 2 of Part C; each B requires 5 of C. there are 160 units of C available. Net requirements for C are:
a) 115
b) 175
c) 240
d) 690
e) 700
Please choose right answer also Explain how you have calculated it.