1. You have to prepare a Construction Programme for a complex multi level project where activities can logically be inprogress, concurrently on each level.

What specific major advantages are there in preparing a manual hand written logic programme, showing the activity logic connections and durations. Before attempting to data entry them into a computer generated programme like Microsoft Project?

List and explain briefly two (2) advantages

2. What is the major advantage to the Management of a construction project to know what activities in the construction program are non-critical and the amount of total float time for each activity

List and describe the advantages

3. If you add up all the total floats (stacks) of separate chains of non critical activities the total is of vital information for managing the project to finish in the shortest time

True of False?

4. During the progression of a commercial construction project inevitably actual progress is delayed behind the planned progress from the construction programme. Once identified by regular monitoring, what options are available for site management to ‘make up' lost time, to prevent financial loss consequences from Liquidated Damages in the head contract?

Describe in detail an action you can initiate to get back on programme.

5. When drafting the initial Construction Programme for a commercial project. What information/data should be considered to allow for anticipated delays? List four possible issues.

· Seasonal inclement weather:

· Sub-contractor delays:

· Material supplier delays:

· Industrial site issues:

6. Site management staff during the construction process are constantly required to manage the finances of the project by using ‘Cost Benefit' analysis processes

For example, to overcome identified loss time on a project one option is utilising existing manpower resources to work additional daily hours on ‘overcome penalty rates' to make up lost time.

What offsetting benefits can be justified to balance out the additional overtime costs?

List three (3)

7. When preparing the initial Construction Programme the programmer has to take into account some legal requirements included in the Head Contract

List three (3) specific generic commercial contract clauses that would be included.

8. Building Consultants engaged by the Architect on a commercial Construction Project are involved in the documentation of services in the Design phase. Identify circumstances in which these Building Consultants would be involved during the construction of a commercial project. List two (2) circumstances which may affect the Programme.

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M92857399
  • Price:- $30

Priced at Now at $30, Verified Solution

Have any Question?


Related Questions in Operation Management

Companies are shifting from evaluating performance to

Companies Are Shifting from Evaluating Performance to Developing Talent: Will It Motivate Employees? Rigid rankings hinder the teamwork and risk-taking necessary for innovation. But what combination of methods works best ...

1 what are three of the guarantees in the bill of rights2

1. What are three of the guarantees in the Bill of Rights? 2. What were the roles of government and business from the Civil War to the Great Depression ? 3. What are the traditional differences between Republicans and De ...

1 explain the importance for tracking and evaluating the

1. Explain the importance for tracking and evaluating the performance of the purchasing function. 2. Most of the time strategic planning is a part of the executive staff's role. Do you think the entire strategic plan sho ...

1 what affect does a successful employee engagement

1. What affect does a successful employee engagement strategy have on the workplace? 2. In making cheese, companies test milk for somatic cell count to prevent diseases. They also test for bacteria to determine how clean ...

The mcdonalds case offers us a view on many issues what is

The McDonalds case offers us a view on many issues. What is our brand identity? Who are our target customers? Why do those customers buy? Let’s first look at each from three perspectives: McDonalds in the early Kroc year ...

The crystal company is a software developer with prod- ucts

The Crystal Company is a software developer with prod- ucts in the payroll and personnel records areas. Joshua and Alyson Bennett started the company fifteen years ago. The Bennetts both have significant experience in pr ...

1 what is tenet healthcares structure amp strategy current

1. What is Tenet Healthcares: Structure & Strategy, Current Structure, Components of Strategy, Competitive Strength, and provide a Summary of the organization. 2. Using an example of a private education institution discu ...

In regards to the namibian justice system1 briefly discuss

In regards to the Namibian justice system 1. Briefly discuss factors affecting contractual capacity 2. Briefly discuss the different forms of breach of contract 3. Briefly discuss how a contract can be terminated Answer ...

Analyse the purchase decision process for1 a candy bar2 an

Analyse the purchase decision process for: 1. A candy bar 2. An automobile Detail each step in the consumer decision process for a "typical" buyer. For example, explain how a person "becomes aware" of the want/need. Next ...

What is the difference between costbenefit evaluation and

What is the difference between cost/benefit evaluation and cost-effectiveness evaluation? When would you use each, and why? the answer needs to be 200-word count, please What is the difference between cost-effectiveness ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As