Ask Operation Management Expert

Managing Project Team

The answer for each question is indicated by a .

1:Which of the following is commonly associated with high-performing project teams?

A)Risk taking is controlled and not allowed to jeopardize the overall project

B)Roles and specific responsibilities are well-defined

C)A degree of competition among team members is encouraged

D)Mistakes are viewed as opportunities for learning

E)Team members are selected with similar talents to enhance cohesion

2:During which stage of team development do close relationships develop and the group demonstrates cohesiveness?

A)Norming

B)Storming

C)Performing

D)Adjourning

E)Forming

3:During which stage of team development is high performance not a top priority and attention is devoted to wrapping up the project?

A)Norming

B)Storming

C)Performing

D)Adjourning

E)Forming

4:Tom is managing a project team responsible for building a new office building that started this week. He notices that team members are trying out different behaviors to see what is acceptable to the project and personal relations. Which stage of development is the team in?

A)Norming

B)Storming

C)Performing

D)Adjourning

E)Forming

5:Experience and research indicate that high-performance project teams are much more likely to develop under all the following conditions EXCEPT

A)Members are assigned to the project full time

B)Members report solely to the project manager

C)There are 10 or fewer members per team

D)Team members are selected by their managers

E)The project involves a compelling objective

6:Project managers play a key role in developing high-performance project teams. Which of the following is NOT a contributing factor to this role?

A)Conduct project meetings

B)Recruit team members

C)Manage a reward system

D)Manage conflict

E)Report progress to top management

 

7:There are two important factors that affect the recruitment of project members. Which of the following is one of those factors?

A)The budget available

B)The size of the project

C)The management structure being used to complete the project

D)The level of innovation and technical expertise needed

E)Organizational culture

8:The first project meeting is critical to the early functioning of the project team. Which of the following is NOT true regarding this meeting?

A)An overview of the project's scope and objectives should be addressed

B)Interpersonal interaction concerns should be addressed

C)The project manager must model how the team will work together

D)The meeting will need to be as long as necessary to cover the main objectives of a first meeting

E)The meeting should be productive, well-organized and realistic.

9:The project manager must quickly establish operational ground rules for how the team will work together. These include planning, tracking, managing change, and relationship decisions. Which of the following is an example of a planning decision?

A)What departments will the team need to interact with during the project?

B)What are the specific roles and responsibilities of all the participants?

C)Who will generate and distribute reports?

D)How will changes be documented and evaluated?

E)How will progress be assessed?

10:Establishing a team identity is facilitated by

A)Team members working in a common space

B)Creation of a project team name

C)Effective use of meetings

D)Team rituals

E)All of these are facilitators of establishing a team identity

11:Individual rewards for outstanding work would NOT include:

A)Letters of commendation

B)Public recognition

C)Desirable job assignments

D)Judiciously making exceptions to the rules

E)All of these are examples of individual rewards for outstanding work

12:The first step in facilitating group decision making is to

A)Call a meeting to discuss the problem

B)Identify the problem

C)Agree that there is a problem

D)Quantify the problem

E)Generate alternatives

13:Which of the following would be an appropriate situation to require facilitating group decision making?

A)A mechanical engineer is stuck trying to meet performance criteria for a prototype

B)When strong group commitment is needed to decide methods to reduce project scope

C)Expectations are unclear regarding a specific task

D)Materials needed to finish a custom kitchen have not been determined

E)Dysfunctional conflict between two project team members needs to be resolved

14:During the delivery phase of a project's life cycle, the most significant source of conflict is

A)Schedules

B)Priorities

C)Technical

D)Procedures

E)Costs

15:When a project manager reduces the intensity of the conflict by smoothing over differences or interjecting humor when dysfunctional conflict arises, they are attempting to _________ the conflict.

A)Eliminate the conflict

B)Control the conflict

C)Mediate the conflict

D)Arbitrate the conflict

E)Encourage the conflict

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M92202447
  • Price:- $10

Priced at Now at $10, Verified Solution

Have any Question?


Related Questions in Operation Management

Conflictdefine functional versus dysfunctional conflict in

Conflict Define functional versus dysfunctional conflict in a work group and explain how you can increase functional conflict and decrease dysfunctional conflict. Develop a response that includes examples and evidence to ...

For this assignment you will need to find 2 articles in

For this assignment, you will need to find 2 articles in business that can help describe what are IT strategic initiative being undertaken by an organization are like. Choose a different organization for each of the arti ...

Coping with problems joe is a little nervous he has just

Coping With Problems Joe is a little nervous. He has just been transferred from another plant to take over a production line. Production is down and there is a serious problem with absenteeism. To make matters worse, the ...

Over 30 years ago michael porter identified a holistic

Over 30 years ago Michael Porter identified a holistic approach to understanding how competitive forces shape strategy. He posited that the only way to truly insulate an organization from underlying economic volatility i ...

You are the contracting officer for an air-to-ground

You are the contracting officer for an air-to-ground missile development program. A contract for pre-production models of the missile was awarded by your predecessor and the contractor is behind schedule. In a program me ...

The ikea case provides an excellent opportunity to apply

The IKEA case provides an excellent opportunity to apply strategic management concepts to a large privately-held company that is expanding into India. IKEA is a Netherlands-based Swedish company with a presence in 44 cou ...

Can you answer for me the following questions about social

Can you answer for me the following questions about social loafing and the three main causes of free-riding. 1. Give a description of the phenomenon of social loafing. 2. Give a description of the phenomenon of free-ridi ...

1 analyzing the bridgestonefirestone and ford motor company

1. Analyzing the Bridgestone/Firestone and Ford motor company, is it sufficient to use the ISO/QS 9000 standards as the main basis of vendor/product selection? 2. What position to these cars company ( 1. Volkswagen, 2. F ...

Research the effect of primary and secondary seat belt laws

Research the effect of primary and secondary seat belt laws on the occurrence of motor-vehicle injuries and fatalities. Explain how epidemiologic studies influenced the development of current seat belt laws. Describe how ...

Please provide a brief paragrap of the key takaways from

Please provide a brief paragrap of the key takaways from each of the following topics: Designing Clear Visuals in business reports Designing Successful Documents and Websites Writing Winning Proposals

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As