LS Hydrogeology is a water and minerals exploration company. It was recently commissioned by the Zambian government to make hydro geological maps which would be obtained at different locations around Zambia. The assignment would involve explorations, sample analysis onsite and computer-graphic displays to produce maps. Managing the preparation for the whole assignment was the responsibility of the project engineer, Bill Kalinda. Bill, who had recently graduated from his MSc Project Management course at the University of Lusaka, knew that he would need to keep a tight grip on the arrangements for the explorations to start successfully. The explorations would start at the end of May and the final targeted site would be explored at the end of July. The hydrogeological maps are required between early July and late August, so any delay either in exploration or in producing the maps would cause considerable complications.

The company had known that it would be commissioned to make the hydro geological maps since December, but Bill had only been allocated the job to start in first week of February! His first act was to list the various jobs which would have to be done before explorations could start. He then discussed each job with the part of the company which would carry it out, to try to understand what decisions would need to be made before they could start on their jobs. The jobs which needed to be done prior to the start of the explorations are listed below together with some details. Note the jobs’ IDs in brackets where arbitrarily allocated.

The project engineer’s responsibilities (as well as managing the whole project) included:

(a) Scheduling the Sites: would take about two weeks to finalize and could be started straight away.

(b) Defining the field work routing: would need discussions with the chief designer and would take about four weeks of considering alternative designs before finalizing the concept, but could be started straight away.

(e) Specifying computer-graphic displays: again in consultation with the chief designer, it would take about a week but could not be started until all the detailed planning had been finalized.

The design department’s responsibility was:

(f) Producing designs for field work routing: would take about three weeks but could be started only after completion of the detailed planning.

The project planning department’s responsibilities were:

(c) Secure exploration sites from the Ministry of Minerals and Water Development: a one- week job which could be started as soon as the sites had been decided by Bill.

(d) Detailed planning: the preparation of detailed plans and schedules, a two-week task which could be started once the design concept had been finalized and the sites secured.

(g) Printing field work routing charts: an outside printer could be given this job as soon as the designs for field work routing had been prepared by the design department. The printer usually quoted a four-week delivery from receipt of the designs.

(h) Printing the display posters: again depended on the preparation of the designs for field work routing but could be delivered within two weeks of the designs being ready.

(i) Ordering the exploration vehicles: a trailer truck and ancillary vehicles were needed which could be ordered on completion of the detailed planning; delivery of the vehicles would take about six weeks.

(j) Writing the customised graphic display software: contracted out to a software house, it would take about four weeks but could only be started after the computer graphics had been specified by the project engineer and chief designer.

(n) Final testing and Kickoff: the project planning department were finally responsible for getting the ‘whole act together’ immediately prior to explorations. Testing could only start once the field work routing charts had been printed, the vehicles fully fitted out and customized and the exploration staff trained. Final tests and kickoff should take around a week but, if things went wrong at any stage, could take longer.

The workshop’s responsibility was:

(k) Customizing and fitting out the vehicles: after the exploration vehicles are delivered and the designs for field work routing agreed and the computer-graphics software finished, the vehicles could be fitted out and customized for the explorations; this would normally take around two weeks.

The personnel department was responsible for:

(l) Recruiting the exploration staff: these were the people who did the actual work in the field;

they could be recruited as soon as the detailed planning was completed. Usually it took two weeks to recruit all the exploration staff.

(m) Training the promo staff: once all exploration staff had been recruited they would need training – a one-week task.

Requirements:

(a) Prepare an Activity Logic Table for this project.

(b) Can Bill get the project together in time to start explorations on schedule? Show workings.

(c) Name the jobs which Bill will have to manage particularly closely? Why?

(d) What other general advice would you give Bill to help him to manage this project?

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M93115119

Have any Question?


Related Questions in Operation Management

One criticism of both the product cost percentage and

One criticism of both the product cost percentage and contribution margin methods used for determining menu prices is that both are based primarily on the cost of food (or beverage) and ignore the cost of labour. In many ...

Inventory managementa george is attempting to perform an

Inventory Management (a) George is attempting to perform an inventory analysis on his most popular products. Annual demand for this product is 5000 units; unit cost is K200,000; carrying cost is considered to be approxim ...

Rview the 5 personality traits describe in chapter 10

Review the 5 personality traits describe in chapter 10 ( understanding individual behavior) 1- Describe 2 of the 5 traits ( extroversion, agreeableness, conscientiousness, emotional stability, openness to experience) tha ...

Government allegation and prosecution of white collar crime

Government allegation and prosecution of white collar crime is a major risk for corporations and management. Complying with all laws and regulations has never been more important. For this discussion post, you will read ...

Enterprise provide the following information on the

Enterprise: provide the following information on the enterprise car rental Overview and History Financial Data: Revenues (or Budget) for the past three years Rationale – why does this firm/organization appeal to you?

If you are negotiating for a better grade or better price

If you are negotiating for a better grade or better price on a new car or a raise at work, how do you useaffective language to get what you want. Do you have a good story about a successful negotiation you had in the pas ...

What is transformational leadership why do people consider

What is transformational leadership? Why do people consider Walt Disney to be a transformational leader? How do these types of leaders change industries, communities, and influence society? What characteristics do they h ...

Assignmentin 1-2 pages answer the following questionswhat

Assignment In 1-2 pages, answer the following questions: What company will you research and what makes it interesting from an Operations Management perspective? What do you already know about this topic and what research ...

1 ask someone to tell you about their best and wort job

1. Ask someone to tell you about their best and wort job interviews. What advice can they give you about how to prepare yourself? 2. Should the availability of alternative work arrangements for private sector employees i ...

Write requirements for a game note you are not writing out

Write Requirements For a Game. Note: You are NOT writing out the code. The Requirements should focus on what you want the game to do… think Shall Statements. If you had a developer working for you, how would you describe ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As