Let the following two mutually exculsive projects, each of which need the initial investment of $30,000 and give cash inflows of $60,000 as given below. This organization has 15% cost of capital.

Year Project A Project B
0 ($30,000) ($30,000)
1 $30,000 $10,000
2 $20,000 $20,000
3 $10,000 $30,000

Using above paybak criterion, which is the most desirable project?

project A, project B, both & A & B are equally suitable, or niether A or B are acceptable - describe answer and why?

 

Business Management, Management Studies

  • Category:- Business Management
  • Reference No.:- M933632

Have any Question?


Related Questions in Business Management

Assignments - reflection papersfrom book resonant

Assignments - Reflection Papers FROM book resonant leadership(richard boyatzis. annie mckee) These are reflective essays about the work assigned in the chapters and your reflection on the course content that is associate ...

In class we were discussing different types of learningwhat

In class we were discussing different types of learning What is the difference between Institutional Learning and System Learning? Is it possible to transition from one to the other in the business setting?

Discuss the transportation and logistics management and its

Discuss the transportation and logistics management and its impact on various economic activities.

What is an editorwhat is a text formattername the editors

What is an editor? What is a text formatter? Name the editors that the UNIX operating system supports. Name the vi modes. Name the keys that place the vi editor in the text input mode. Explain how the vi editor uses buff ...

Can anyone help with the following questionsin the search

Can anyone help with the following questions? In the "Search" component of Amazon's strategy, why do you think companies choose Amazon search over Google search? What do you think is the real competitive advantage this h ...

Traditional and agile schedule developments are quite

Traditional and Agile schedule developments are quite different. Agile project management was originally developed to do software development. Could a traditional process be successfully used to develop a new software pr ...

A consumer consumes two goods x1 and x2 to figure how the

A consumer consumes two goods, X1 and X2. to figure how the quantity demanded of the good X1 changes after the price of the good X2 rises, the relationship between two goods must be found beforehand. what kind of relatio ...

What techniques and communication would you use when

What techniques and communication would you use when identified problems and issues in your workplace. And what is the follow up action you would take after?

Any help will be appreciatedscenarionbspyou are a

Any help will be appreciated Scenario: You are a networking and communications consultant working for HoustonComm Services, Inc, further referred to as HCS. HCS is a company providing technology consulting services to st ...

After reviewing the harvard case study titled alaska

After reviewing the Harvard Case Study titled "Alaska Airlines: Navigating Change" What are the key problems/issues. What are the consequences of these problems/issues?

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As