Ask Business Management Expert

Internet Case - Cranston Construction Company

Cranston Construction Company

The Cranston Construction Company is a small Mississippi construction company that undertakes building projects of a medium-to large-scale nature based on local and statewide needs. Although the company is capable of operating outside of its native state, it usually does not bid on out-of-state business. It maintains an office with a small staff and usually has several construction projects going on at the same time. Cranston has just received the contract for construction of a new humanities building on the campus of Northern Mississippi State University. 

Although the university and the State Building Commission are pleased to have completed negotiations for the new building, a significant task lies ahead for Mr. Daniel Cranston, the president of Cranston Construction Company. He must select a project manager and arrange for allocation of necessary resources for construction. He must then work with the project manager to develop a schedule for constructing the building in order to assist in the timely decision-making that involves financial needs and shifting of equipment from other job sites. 

Mr. Cranston decides that the detailed planning, layout, and scheduling can be provided by his project manager. The project manager will further be delegated total authority for the construction operations, the execution phase of the project. Based on past experience, Mr. Cranston makes up a job breakdown with approximate costs (shown in Table 1). Since the bid was for over $1 million, these costs represent company targets and are confidential. Although Cranston does not have significant experience with critical path analysis, he also makes up the activity list and time allowances (shown in Table 2). These time allowances represent the span between the earliest date he thinks each activity can begin and the latest date by which each should end. 

TABLE 1 Job Breakdown, Humanities Building

NumberActivity

1.Sales tax, bond, and insurance$22,000

2.General conditions25,000

3.Site work8,000

4.Reinforcing steel57,000

5.Concrete footings17,000

6.Concrete grade beams14,000

7.Structural concrete115,000

8.Structural and miscellaneous steel21,000

9.Masonry (includes stone)125,000

10.Roofing and sheet metal and insulation16,000

11.Doors and frames2,000

12.Architectural and miscellaneous metal and accessories5,000

13.Metal windows2,000

14.Lath and plaster24,000

15.Ceramic and marble5,000

16.Millwork34,000

17.Hardware9,000

18.Resilient floor10,000

19.Glazing and store front20,000

20.Acoustic ceiling10,000

21.Painting10,000

22.Elevator19,000

23.Carpet8,000

24.Finish grade and site work10,000

25.Clean up and move out4,000

26.Miscellaneous labor and materials20,000

Total Contract Price$612,000

TABLE 2 Project Activities and Duration

NumberActivityTime Allowed (days)

1.Sales tax, bond, and insurance35

2.Move in, tool house general conditions35

3.Clean, clear, excavate, and grade28

4.Reinforcing steel217

5.Concrete footings35

6.Concrete grade beams35

7.Structural concrete framing and slabs35

8.Structural and miscellaneous steel210

9.Masonry and stone231

10.Roofing and sheet metal80

11.Metal doors and frames203

12.Architectural and miscellaneous metal and accessories266

13.Metal windows231

14.Lath and plaster154

15.Ceramic tile and marble30

16.Millwork234

17.Finish hardware133

18.Resilient floor161

19.Glazing and store front203

20.Acoustic ceiling35

21.Painting161

22.Elevator119

23.Carpet35

24.Finish grade and site work28

25.Clean up and move out49

With these initial efforts, Mr. Cranston calls in Mr. Henry Nolton to discuss his appointment as project manager. After a lengthy discussion, Mr. Nolton accepts the appointment but makes the following statement to Mr. Cranston: 

"Your cost targets are probably reasonable; however, your time estimates and activity list do not really provide believable information. According to your figures, the project will be finished in less than 370 days and, therefore, you will not incur any penalty costs. However, if most of your time estimates are close to being correct, then I believe that the project will take longer than 370 days. As an example, let me point out that your duration times look like total time allowances rather than activity times. Take the activity of "architectural and miscellaneous metals." I'd say that this would take about two weeks to complete and could be one of the last items accomplished, probably following completion of all the stairwells." 

"Another major problem with your listing is that we'll be using reinforcing steel with all of the concrete work and, since it's a three-story building with a penthouse, we'll be doing concrete activities floor by floor. Thus, in order to schedule and control this job, I need to decide on an activity list which is based on the actual sequence of construction, floor by floor. floor concrete, the middle-floor columns and then the middle-floor concrete framing may be completed similar to the first-floor logic. After framing is complete, middle floor door frames, upper-floor concrete and lath and plaster activities can start. Lower floor masonry and middle-floor door frames must be complete before middle floor masonry can begin. Following lath and plaster, ceramic tile and marble can be placed. After the stairwells are complete, hardware, architectural, and miscellaneous metals can be installed." 

"As with the first two floors, upper-floor columns are emplaced following the upper floor concrete work. Next, upper-floor concrete framing can be completed. At this juncture, upper-floor door frames, roofing, and elevator activities can begin. Once these three activities are completed, plus completion of middle-floor masonry, the upper floor masonry, penthouse work, and ceiling work can be started. Following ceiling work, painting can begin and must be finished before tiling and carpeting which follow millwork. The millwork and finish grading start after upper-floor masonry and penthouse activities." 

Upon hearing this, Mr. Cranston decides to modify the activity list to make it more useful and more accurate. Working together, Mr. Cranston and Mr. Nolton put together Table 3 which gives all the relevant information. 

Table 3. Revised List of Activities and Times

LabelActivity Immediate

Predecessors Duration (days) 

ALayout, Excavate, and Grade - 28

BTax, Bond, & Insurance - 21

CMove In Tool House, General Conditions - 7

DGrade Beams A, B, C 11

EFoundation, Concrete footings A, B, C 11

FLower Floor Concrete D, E 10

GLower Floor Columns F 21

HLower Floor Frame G 35

IMiddle Floor Concrete H 12

JMiddle Floor Columns I 23

KMiddle Floor Concrete Frame J 37

LUpper Floor Concrete K 14

MUpper Floor Columns L 23

NUpper Floor Concrete Frames M 37

OUpper Floor Door Frames N 14

PRoof Slab, Beams, Sheet Metal N 21

QElevator N 21

RLathe & Plaster K 21

SUpper Floor Masonry, Interior Doors O, P, Q, II21

TPenthouse Steel, Concrete, and Masonry O, P, Q, II21

UCeilings O, P, Q, II42

VPaint U 42

WMillwork S, T 42

XFinish Grade, Sitework S, T 28

YTile & Carpet V, W 21

ZClean Up, Inspect, and Move Out X, Y, AA, CC, FF, GG2

AACeramic Tile & Marble R 14

BBStairwells H 35

CCHardware, Architectural and Miscellaneous Metals BB 14

DDLower Fl. Door Frames H 14

EELower Floor Masonry & Interior Doors DD 35

FFExterior Doors H 21

GGGlazing & Store Front H 35

HHMiddle Floor Dr. Frame K 14

IIMiddle Floor Masonry, Interior Doors EE, HH 35

1.Acting as Mr. Nolton's administrative assistant, draw a network to represent this project.  Then develop a table showing the activities from Table 3, their durations, their earliest start, earliest finish, latest start, latest finish, and slack times.  Identify the activities on the critical path.

2.Write a report to Mr. Nolton addressing the problems of project duration and specifying which activities may require the closest management attention. If it appears that the project will not be finished on time, identify the activities which might be considered for crashing if relevant time and cost information could be found.

Business Management, Management Studies

  • Category:- Business Management
  • Reference No.:- M92005103
  • Price:- $35

Priced at Now at $35, Verified Solution

Have any Question?


Related Questions in Business Management

Name a company that addressed a recent ethical problem in a

Name a company that addressed a recent ethical problem in a positive way. Also, explain how or if this positively affects us as a community?

When it is appropriate to use the trade-off process what

When it is appropriate to use the trade-off process. What conditions apply, and the technical evaluation criteria that might be used?

Need help with a essay with the following phrase for

Need help with a essay with the following phrase for analyzing : " Capitalism is at the heart of how people and organisations are managed in contemporary society" May i ask for a better explanation of the question? Also ...

How could these three tenets of the auburn creed be used to

How could these three tenets of the Auburn Creed be used to motivate others: "I believe that this is a practical word and that I can count only on what I earn. Therefore, I believe in work, hard work." "I believe in educ ...

How can these two tenets of the auburn creed by used in

How can these two tenets of the Auburn Creed by used in addressing teamwork issues: "I believe in honesty and truthfulness, without which I cannot win the respect and confidence of my fellow men." "I believe in the human ...

Discuss the advantages of having and interacting in a

Discuss the advantages of having and interacting in a diverse workplace. Consider the wide range of ideas and perspectives that a range of team members bring to a team, that are of differing ages, ethnic backgrounds and ...

Parmigiano-reggiano global recognition of geographical

Parmigiano-Reggiano: Global Recognition of Geographical Indications What historical factors have helped support the consortium's claims for the geographic specificity of Parmigiano-Reggiano and Parmesan? What are the eco ...

Communication planthis communication plan will be a roadmap

Communication Plan This communication plan will be a roadmap on how the new division will best be able to communicate with Biotech's corporate headquarters, suppliers, other divisions, and internally. This should lay out ...

Discuss strategies to obtain feedback from a customer and

Discuss strategies to obtain feedback from a customer and clients when working in sales.

Describe different networking methods and the advantages

Describe different networking methods and the advantages and disadvantages of them?

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As