(a) A food products' company is contemplating the introduction of a 07 revolutionary new product with new packaging or replacing or the existing product at much higher price (S1). It may even make a moderate change in the composition of the existing product, with a new packaging at a small increase in price (S2), or may mall a small change in the composition of existing product, backing it with the word ‘New' and a negligible increase in price (S3). The three possible states of nature or events are: (i) high increase in sales (N1), (ii) no change in sales (N2) and (iii) decrease in sales (N3). The marketing department of the company worked out the payoffs in terms of yearly net profits for each of the strategies of three events (expected sales). This is represented in following table:

 

States of Nature

Strategies

N1

N2

N3

S1

7,00,000

3,00,000

1,50,000

S2

5,00,000

4,50,000

0

S3

3,00,000

3,00,000

3,00,000

Which strategy should the concerned executive choose on the basis of

(a) Maximum criterion (b) Minimax regret criterion

(c) Maximax criterion (d) Laplace criterion?

(b) State and discuss the methods of solving an assignment problem. How is the Hungarian method better than other methods for solving assignment problem?

Q2. (a) Solve the following LPP:

Maximise Z=8X1 - 4X2

Subject to 4X1 + 5X2 ≤ 20
-X1 + 3X2 ≥ -23
X1 ≥ 0, X2 unrestricted in sign

(b) What is trans-shipment problem? Explain how it can be formulated and solved as a transportation problem.

OR

(b) Solve the following transportation problem. Obtain the initial solution by NW corner rule.

 

To

 

1

2

3

4

Supply

 

From

A

7

3

8

6

60

B

4

2

5

10

100

C

2

6

5

1

40

Demand

20

50

50

80

200

(a) A timber merchant manufactures three types of plywood the data below give the production hours per unit in each of three production operations, maximum time available, and profit per unit.

 

Operation (Hours)

Profit per Unit (Rs)

Plywood

I

II

III

Grade A

2

2

4

40

Grade B

5

5

2

30

Grade C

10

3

2

20

Maximum Time Available

900

400

600

 

How many units of each grade of plywood should be produced to maximize the total profit?

(b) a) A machine M1 Costing Rs 9,000 has a maintenance cost of Rs 200 in the first year of its operation which rises by Rs 2,000 in each of the successive years. Assuming that the machine replacement can be done only at the end of year, Determine the best age at which the machine be replaced.

b) There is an offer to replace the machine M1 which is a year old, by another machine M2 which cost Rs 8,000. The machine M2 needs Rs 2,000 to be spent on installation, has no salvage value and requires Rs 400 on maintenance in the first year followed by an increase of Rs 800 per annum in the yearly expenditure on maintenance. Should the machine M1 be replaced by Machine M2? If so, When?

OR

(a) A company plans to assign 5 salesman to 5 district in which it operates. 07 Estimates of sales revenue in thousands of rupees for each sales man in different districts are given in the following table. In your opinion, what should be the placement of the salesmen if the objective is to maximise the expected sales revenue?

Expected Sales Data

Salesman

District

D1

D2

D3

D4

D5

S1

40

46

48

36

48

S2

48

32

36

29

44

S3

49

35

41

38

45

S4

30

46

49

44

44

S5

37

41

48

43

47

(b) A group of process plants in an oil refinery are fitted with valves. Over a period of time the failure pattern of these 400 valves has been observed and it is as follows :

Month

:

1

2

3

4

5

6

7

8

Total

Number of valves failing

:

8

20

48

104

120

56

32

12

400

It costs Rs 100 to replace each valve individually. If all the valves are replaced at a time, it costs Rs 50 per valve.

The maintenance department is considering following replacement policies
:

a) To replace all valves simultaneously at fixed intervals, in addition to replacing valves as and when they fail.
b) To replace valves as and when they fail. Suggest an optimal replacement policy.

(a) Solve the following transportation problem for maximum profit.

Per Unit Profit (Rs)
  Market

 

A

B

C

D

 

Warehouse

X

12

18

6

25

Y

8

7

10

18

Z

14

3

11

20

(b) Find the sequence that minimises the total elapsed time required (T) in completing the following jobs. Each job is processed in the order ABC. Also, calculate T.

Job

 

1

2

3

4

5

6

7

Machine A

:

10

8

12

6

9

11

9

Machine B

:

6

4

6

5

3

4

2

Machine C

:

8

7

5

9

10

6

5

(a) The data for a project are :

Activity

Preceding Activity

Time (in weeks)

Cost (in Rs)

Normal

Crash

Normal

Crash

A

None

3

2

18,000

19,000

B

None

8

6

600

1,000

C

B

6

4

10,000

12,000

D

B

5

2

4,000

10,000

E

A

13

10

3,000

9,000

F

A

4

4

15,000

15,000

G

F

2

1

1,200

1,400

H

C, E, G

6

4

3,500

4,500

I

F

2

1

7,000

8,000

a) Draw a project network diagram and find the critical path.

b) If a deadline of 17 weeks imposed for completion of the project, what activities will be crashed, what would be the additional costs, and what would be the critical activities of the network after crashing?

(b) Give the various sequencing models that are available for solving sequencing problems. Give suitable examples.

(a) The following table shows for each activity needed to complete the project the normal time, the shortest time in which the activity can be completed of a building contract and the cost per day for reducing the time of each activity. The contract includes a penalty clause of Rs 100 per day over 17 days. The overhead cost per day is Rs 160.

Activity

Normal time in days

Shortest time in days

Cost of Reduction per day (Rs)

1-2

6

4

80

1-3

8

4

90

1-4

5

3

30

2-4

3

3

-

2-5

5

3

40

3-6

12

8

200

4-6

8

5

50

5-6

6

6

-

The cost of completing the eight activities in normal time is Rs 6500.

a) Calculate the normal duration of the project, its cost and the critical path.

b) Calculate the cost/time function for the project and state:
i. The lowest cost and associated time.
ii. The shortest time and associated cost.

(b) How would you deal with replacement of items that fail completely and suddenly?

OR

Q.5 (a) Give general structure of queuing system and explain. Illustrate some queuing situations.

(b) A salesman wants to visit cities 1, 2, 3 and 4. He does not want to visit any city twice before completing the tour of all the cities and wishes to return to his home city, the starting station, Cost of going from one city to another in rupees is given in table below.

 

 

From City

To City

 

1

2

3

4

1

0

30

80

50

2

40

0

140

30

3

40

50

0

20

4

70

80

130

0

Find the Least cost rout.

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M92006573
  • Price:- $75

Guranteed 36 Hours Delivery, In Price:- $75

Have any Question?


Related Questions in Operation Management

Conflictdefine functional versus dysfunctional conflict in

Conflict Define functional versus dysfunctional conflict in a work group and explain how you can increase functional conflict and decrease dysfunctional conflict. Develop a response that includes examples and evidence to ...

For this assignment you will need to find 2 articles in

For this assignment, you will need to find 2 articles in business that can help describe what are IT strategic initiative being undertaken by an organization are like. Choose a different organization for each of the arti ...

Coping with problems joe is a little nervous he has just

Coping With Problems Joe is a little nervous. He has just been transferred from another plant to take over a production line. Production is down and there is a serious problem with absenteeism. To make matters worse, the ...

Over 30 years ago michael porter identified a holistic

Over 30 years ago Michael Porter identified a holistic approach to understanding how competitive forces shape strategy. He posited that the only way to truly insulate an organization from underlying economic volatility i ...

You are the contracting officer for an air-to-ground

You are the contracting officer for an air-to-ground missile development program. A contract for pre-production models of the missile was awarded by your predecessor and the contractor is behind schedule. In a program me ...

The ikea case provides an excellent opportunity to apply

The IKEA case provides an excellent opportunity to apply strategic management concepts to a large privately-held company that is expanding into India. IKEA is a Netherlands-based Swedish company with a presence in 44 cou ...

Can you answer for me the following questions about social

Can you answer for me the following questions about social loafing and the three main causes of free-riding. 1. Give a description of the phenomenon of social loafing. 2. Give a description of the phenomenon of free-ridi ...

1 analyzing the bridgestonefirestone and ford motor company

1. Analyzing the Bridgestone/Firestone and Ford motor company, is it sufficient to use the ISO/QS 9000 standards as the main basis of vendor/product selection? 2. What position to these cars company ( 1. Volkswagen, 2. F ...

Research the effect of primary and secondary seat belt laws

Research the effect of primary and secondary seat belt laws on the occurrence of motor-vehicle injuries and fatalities. Explain how epidemiologic studies influenced the development of current seat belt laws. Describe how ...

Please provide a brief paragrap of the key takaways from

Please provide a brief paragrap of the key takaways from each of the following topics: Designing Clear Visuals in business reports Designing Successful Documents and Websites Writing Winning Proposals

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As