In this homework assignment, you will be working through two crashing problems and four earned value problems. All the information you need is included within this Homework packet. Make sure you answer all parts of the questions in their entirety.

Once you have worked through the problems, please post your responses to the Dropbox. Please refer to the course Syllabus for the due date.

PROBLEM 1

Use the network diagram below and the additional information provided to answer the corresponding questions.

a) Give the crash cost per day per activity.

b) Which activities should be crashed to meet a project deadline of 10 days at minimum cost? What is the cost impact of crashing these activities?

c) Find the new budget (or cost of the project).

PROBLEM 2

Use the network diagram below and the additional information provided to answer the corresponding questions.

a) Give the crash cost per day per activity.

b) Which activities should be crashed to meet a project deadline of 13 days at minimum cost? What is the cost impact of crashing these activities?

PROBLEM 3

Month

AC

PV

EV

22

$540

$523

$535

a) Calculate the cost variance (CV).

b) Is the CV over or under budget?

c) Calculate the schedule variance (SV).

d) Is the SV ahead of or behind schedule?

PROBLEM 4

Month

AC

PV

EV

5

$34

$42

$39

a) Calculate the cost performance index (CPI).

b) Is the project cost efficient or not efficient?

c) Calculate the schedule performance index (SPI).

d) Is the schedule efficient or not efficient?

PROBLEM 5

Day

AC

PV

EV

65

$550

$735

$678

a) Calculate the cost variance (CV).

b) Calculate the cost performance index (CPI).

c) Calculate the schedule variance (SV).

d) Calculate the schedule performance index (SPI).

e) Given these data, what should a project manager do with respect to this project?

PROBLEM 6

Day

AC

PV

EV

65

$760

$735

$678

a) Calculate the cost variance (CV).

b) Calculate the cost performance index (CPI).

c) Calculate the schedule variance (SV).

d) Calculate the schedule performance index (SPI).

e) Explain the project performance in terms of efficiency, budget, and schedule. What should the project manager do for the project?

Business Management, Management Studies

  • Category:- Business Management
  • Reference No.:- M92031597
  • Price:- $30

Priced at Now at $30, Verified Solution

Have any Question?


Related Questions in Business Management

Discuss the principle components of an effective and

Discuss the principle components of an effective and compelling vision. Then present the vision for your current/previous organization, detailing how you would improve upon that vision to ensure that it conforms to your ...

In the book contagious the author indicates that throwing

In the book "Contagious" the author indicates that throwing advertising money at a product does not necessarily mean we buy. Consider the "eat more vegetables" campaign, it did not work. WHAT did it lack? Do you agree? E ...

What are the best practices a firm should follow to better

What are the best practices a firm should follow to better ensure compliance with US export controls?

What do you think about the response from the ceo of united

What do you think about the response from the CEO of United? The United Airlines statement reads: "Flight 3411 from Chicago to Louisville was overbooked. After our team looked for volunteers, one customer refused to leav ...

Final project - leadership and strategy planfor this final

Final Project - Leadership and Strategy Plan For this Final Project, you select a pressing health problem affecting a community and develop a leadership and strategy plan for addressing the problem. You link this problem ...

Discussion boardwhat is a smart sustainable city in your

Discussion Board: What is a smart sustainable city in your opinion? Course name: NEW Product and Service Innovation

For this weeks discussion please read the above link titled

For this week's discussion, please read the above link titled "Managing Special Event Risks". After reading the authors' points on executing an event and developing a proper risk management safety plan, what areas of ris ...

Explain the procedure to construct a house of

Explain the procedure to construct a 'House of Quality'.

1nbspsignificance of the study describe the research

1.  Significance of the study . Describe the research questions targeted to be addressed in Article 1, 2 and their significance. 2.  Method of data collection . Describe the methods used in data collection and their appr ...

Tasksgamego a game company specializes in online games for

Tasks GameGo, a game company, specializes in online games for kids. GameGo has hired you to write C++ programs for their business. Draw a Card. Write program to simulate drawing a card. Your program will randomly select ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As