In the following schedule, what is the total amount of uncommitted inventory that the company can promise to new customer requests for the month of June? (Hint: Calculate the ATP corresponding to June week 1, week 2, and week 3. Then, add up all of these values.)
|
|
June
|
July
|
|
|
|
|
1
|
2
|
3
|
4
|
5
|
6
|
7
|
8
|
|
|
|
Forecast
|
50
|
50
|
50
|
50
|
50
|
50
|
50
|
50
|
|
|
|
Customer Orders
|
52
|
35
|
20
|
12
|
|
|
|
|
|
|
|
Projected on-hand inventory
|
23
|
48
|
73
|
23
|
48
|
73
|
23
|
48
|
|
|
|
MPS
|
75
|
75
|
75
|
|
75
|
75
|
|
75
|
|
|
|
ATP
|
|
|
|
|
|
|
|
|
|
|
|
|
A) 106
B) 75
C) 225
D) 110
E) 125